Table of Contents

Preface

P.1 Purpose
P.2 Applicability
P.3 Authority
P.4 Applicable Documents and Forms
P.5 Measurement/Verification
P.6 Cancellation

Chapter 1. NASA's Facilities Program

1.1. Facility Program Content
1.2 Facility Program Best Practices
1.3 Sustainability Requirements
1.4 COF Program Formulation

Chapter 2. Project Development and Planning

2.1 Facility Project Development
2.2 Facility Project Planning

Chapter 3. Design

3.1 Design Coordination
3.2 Architectural-Engineering (A-E) Services
3.3 Public Release
3.4 Management of Design
3.5 Preliminary Engineering Report
3.6 Design Milestones
3.7 BIM Requirement
3.8 Design Reviews
3.9 Mission-Critical Systems
3.10 Facility Activation Plan
3.11 Activation Budget

Chapter 4. Construction

4.1 Acquisition of Construction
4.2 Preparation of the Acquisition Package
4.3 Authority to Advertise
4.4 Receipt of Bids or Negotiation
4.5 Contract Award
4.6 Building Information Modeling
4.7 Construction Management
4.8 Real Property Capitalization
4.9 Project Closeout

Chapter 5. Activation

5.1 Activation
5.2 Facility Outfitting
5.3 Beneficial Occupancy Prior to Completion
5.4 Completion And Acceptance of Installed Systems
5.5 O&M Manuals and Training
5.6 Commissioning

Chapter 6. Disposal/Deconstruction

6.1 Demolition Plan
6.2 Demolition Planning Checklist

Appendix A. Definitions
Appendix B. Acronyms
Appendix C. Compliance Matrix
Appendix D. Facility and Other Related Costs
Appendix E. Demolition Planning Checklist
Appendix F. Reference Documents

List of Figures

Figure 1-1a CoF Project Life Cycle
Figure 1-1b CoF Five-Year Plan
Figure 1-1c Institutional CoF Call and Programming Phase of Planning, Programming, Budgeting, and Execution System
Figure 1-2 CoF Program Management
Figure 1-3a Facilities Project Activities and Funding for Design-Bid-Build
Figure 1-3b Facilities Project Activities and Funding for Design-Build


DISTRIBUTION:
NODIS


This Document Is Uncontrolled When Printed.
Check the NASA Online Directives Information System (NODIS) Library
to Verify that this is the correct version before use: http://nodis3.gsfc.nasa.gov