A. If an emergency requirement exists, the CTO should take the following steps:
Try to locate an existing GSA or NASA-owned asset that may be available for transfer or reassignment (be sure to contact all other NASA Centers);
Obtain a commercial rental or lease vehicle to temporarily fulfill the need until a normal purchase can be made;
Contract for the service or arrange for the existing contractor to secure the asset where economically feasible;
In rare circumstances, it may be appropriate to initiate the process of purchasing a “stock” vehicle from a local dealer’s inventory.