|
NASA Procedures and Guidelines |
||||
This Document is Obsolete and Is No Longer Used.
|
|||||
|
|
|||||
|
|
||||
| | TOC | Preface | Change_Log | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | Chapter7 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | AppendixK | AppendixL | AppendixM | AppendixN | AppendixO | ALL | | |||||
SPECIAL NOTICE: Chapter 4 & 5 of this NPR has been cancelled by NPR 7120.8.
5.1.a NASA advanced technology development (ATD) programs and projects are investments that produce entirely new capabilities or that help overcome technical limitations on a system-of-interest. This document distinguishes between basic and applied research programs and projects, on the one hand, and ATD programs and projects on the other. The principal distinction is that, in the former, a technologist is given adequate time and resources to prove the merits of a new concept, whereas in the latter, a concept has already been shown to be successful enough to warrant further investment in order to make it ready for application. NASA uses Technology Readiness Levels (TRLs) as a maturity measurement technique. (See Appendix F for a description of Technology Readiness Levels.) Basic and applied research generally reflects lower TRL levels, whereas ATD projects reflect TRLs 4 through 6. Because TRLs are somewhat subjective, some ATD projects may fall outside this range. ATD is seen as a bridge between basic and applied research and actual application in NASA or elsewhere.
5.1.b ATD projects may be a part of a program whose sole purpose is technology development, or they may be embedded in a flight systems and ground support program. In both programmatic structures, however, the Program Plan must designate its component ATD projects, and ATD Project Managers must comply with the requirements of the four-part management process described in Chapter 3 as clarified and modified by this chapter. Figure 5-1 shows the ATD project lifecycle.
Figure 5-1. Advanced Technology Development project lifecycle
5.1.c ATD projects present unique management challenges. Often an ATD "project" (within NASA's budget and financial structure) is actually a large collection of tasks, each of which is small in budget and produces a discrete product or service. The Project Manager in this case coordinates the collection of tasks, but is required to create only one Project Plan. Occasionally, an ATD project will be large enough to be Category I or II.34 In this case, additional management requirements are imposed.
5.1.d NASA values technology infusion, whether into NASA flight projects or the U.S. economy as a whole. Flight projects and other users tend to embrace a new technology when sufficient maturity has been aptly demonstrated, and applicability to a mission or missions is abundantly clear. When a user "pulls" a technology into a mission or other use, the ATD Project Manager has successfully infused the technology. This requires close interaction with potential users of the new technology to overcome the many practical design and system integration challenges. To foster higher infusion rates, this document requires ATD projects to identify potential adopters and to ensure that progress is measured not only in terms of maturation level (TRL), but also through quantifiable key performance parameters (KPPs) important to those adopters. The combination of KPPs and TRLs not only enhances progress communication at key milestones, but also provides a more balanced assessment of risks and rewards in ATD projects.
5.2.1 The work that constitutes formulation for an ATD project is mainly project planning and cost estimation. It is expected that some adjustment of management plans and products will be needed to comply with the requirements of Chapter 3, depending on the size, complexity, and priority of the ATD investment.
5.2.2 Requirements: The ATD Project Manager and the project team shall:
5.2.2.a Perform technology portfolio analyses. The Project Manager shall ensure that portfolio analysis studies are conducted to justify technology selections. Techniques such as Alignment Matrices, ROI vs. Risk Matrices, Technology S-curve Maps, etc. can be used to determine the best mix of technologies that will balance the project's risk posture.
5.2.2.b Identify a set of project KPPs (a goal value and a threshold value for each).
5.2.2.c Complete the project estimate.
5.2.2.d Prepare a Project Plan containing the elements described in Appendix D, with the following modifications:
5.3.1 To secure approval for ATD projects, the Project Manager shall ensure that project deliverables are clearly defined and that proposed plans allow for quantitative measurements of performance that can be objectively assessed. ATD projects, like other projects, are subject to a NAR with an independent cost estimate (for Category I and II projects) prior to implementation. ATD Project Managers are expected to update the Project Baseline for the NAR; upon approval, the project's NAR Baseline is formally established. The requirements of Section 3.3 apply to ATD projects with the modifications in Section 5.2 above.
5.4.1 ATD project implementation requires continuing interaction between the project team and the user or application community.
5.4.2 Requirements: During implementation, the ATD Project Manager and the project team shall:
5.4.2.a Monitor cost and schedule for breaches as required by paragraph 3.4.3.2e. A breach for ATD projects is measured against cost and schedule growth. The Project Manager shall provide notification to the Program Manager, the MDAA, and the GPMC when the growth in the projected (or actual) cost and schedule needed to deliver the threshold KPPs exceeds ten percent (10%).
5.4.2.b Communicate progress to the Program Manager and user/application community.
5.4.2.c The Project Manager shall ensure that changes to threshold KPPs established in the NAR Baseline are captured as part of updates to the Project Baseline.
5.5.1 It is expected that only rarely will ATD projects be Category I, so Project Managers will normally report to Center and Mission Directorate PMCs. Agency visibility into the progress of ATD projects will occur through program reviews at regularly scheduled QSRs at the Agency PMC, and through any reviews conducted by IPAO of programs containing ATD projects. The requirements of paragraph 3.5.3 apply.
| TOC | Preface | Change_Log | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | Chapter7 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | AppendixK | AppendixL | AppendixM | AppendixN | AppendixO | ALL | |
| | NODIS Library | Program Formulation(7000s) | Search | |