NPR 7120.7
Eff. Date: November 03, 2008
Cancellation Date:

NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements

| TOC | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | ALL |


Chapter 6. Required Gate Products at Key Decision Points

6.1 Gate Products

6.1.1 There are defined program and project management products (and their maturities) expected to be completed before each KDP. These products include documented project plans, design information, technical analyses, project metrics, and documentation of independent assessments. Program and project managers assemble this information in an orderly manner for presentation and discussion at the reviews prior to the KDPs.

Table 6-1 lists the gate products required for programs and describes their required maturity by KDP and major program review. Table 6-2 lists the gate products required for IT and OMSI projects and describes their required maturity by KDP and major project review. Products marked as "Updated" must be analyzed by the program or project, and any required changes made prior to the KDP. The date markings of the documents and their revision histories must be changed to indicate that the analysis occurred, even if changes to the content of the documents were not needed.

NPR 7120.7 Program Gate Products
Products Formulation Implementation
KDP I KDP II KDP III KDP n
FAD Approved      
PCA Approved Updated Updated Updated
Program Plan Approved Updated Updated Updated
Interagency and International Agreements Approved      
PCDR Products Final      
PIR Products   Final Final Final

Table 6-1 Program Gate Products Maturity Matrix

6.2 Waiver Approval Authority

6.2.1 Waivers to requirements in this NPR may be granted by the officials shown in Tables 6-3, 6-4, and 6.5. Waivers are used to adapt the requirements to the scope and scale of Information Technology and Institutional Infrastructure programs and projects.

6.2.2 Waivers with dissent are reviewed and dispositioned by the NASA Deputy Administrator for programs and projects with a life-cycle cost equal to or greater than 10 million dollars and by the OCE, cognizant MDAA or Mission Support Office Official-in- Charge for all other programs and projects, depending on the life-cycle cost.

NPR 7120.7 Project Gate Products
Products Pre-Phase A Phase A Phase B Phase C Phase D Phase E Phase F
KDP A KDP B KDP C KDP D KDP E KDP F  
SCR SRR PDR CDR TRR/ ORR PCR  
Project Planning, Cost, Schedule, and Communication Products
1. FAD Approved Approved (if there was no Pre-Phase A)          
2. Program Requirements on the Project Preliminary Baseline Updated        
3. Work Agreements for next phase Baseline Baseline Baseline Baseline Baseline Baseline  
4. Integrated Baseline   Preliminary Baseline        
5. Governing Body Review products Final Final Final Final Final Final  
6. Software Development/Management Plan as required by NPR 7150.2, NASA Software Engineering Requirements (IT Projects only)   Preliminary Final        
7. Project Plan (refer to Chapter 4; Appendix F provides a template; individual sub-plans can be stand-alone documents)   Preliminary Baseline Updated Updated    
Project Technical Products
1. System Concept Preliminary Baseline          
2.Information/System Security Categorization (IT Projects Only) Preliminary Baseline          
3. System Level Requirements   Preliminary Baseline        
4. System Technical Architecture     Preliminary Baseline      
5. Operations Concept   Preliminary Baseline        
6. Preliminary Design     Baseline        
7. Detailed Design       Baseline      
8. Test Plan, Test Procedures, and Test Cases         Baseline    
9. Training Plan and Training Materials       Preliminary Baseline Updated  
10. As-built and As-deployed Hardware and Software Documentation         Baseline    
11. Operations Handbook       Preliminary Baseline    
12. Project Completion Report           Final  
13. Decommissioning Plan             Final
IT Project Certification Products (IT Projects Only)
Products Pre-Phase A Phase A Phase B Phase C Phase D Phase E Phase F
KDP A KDP B KDP C KDP D KDP E KDP F  
1. Certification that project is ready to transition to the next phase Final Final Final Final Final Final  
2. IT Security Certification and Accreditation of System         Initial Triennial renewal  

Table 6-2 Project Gate Products Maturity Matrix (continued)

Note: The products shown in Table 6-2 are a minimal set. Depending on the nature of the project, other products (e.g., a Disaster Recovery Plan) called out in other policy documents may be required.

6.2.3 Requests for waivers to requirements in this NPR are documented and submitted for approval using the NPR 7120.7 Waiver Form. Prior to the KPD I for programs and KDP B and KDP C for projects, these requests may be documented and attached to a single waiver to assure proper routing and control. Waivers impacting formulation or requiring long lead time may be submitted individually early in formulation. Following KDP I for programs and KDP C for projects, waivers must be submitted individually to the appropriate authorities.

Project Type Project Manager Program Manager MDAA or Mission Support Office Official-in- Charge CIO OCE & OSMA Approval Authority for Waivers with Dissent
IT R A A A A NASA Deputy Administrator
OMSI R A A   A NASA Deputy Administrator

R = Recommends A = Approves I = Informed

Table 6-3 Waiver Approval for Programs and Projects >= $10 million Life-Cycle Cost (LCC)

Project Type Project Manager Program Manager MDAA or Mission Support Office Official- in-Charge CIO OCE & OSMA Approval Authority for Waivers with Dissent
IT R A A A I OCE
OMSI R A A   A* OCE

R = Recommends A = Approves I = Informed

*If the project is implemented at a Center, Center level SMA Approval is required.

Table 6-4 Waiver Approval for Programs and Projects >= $1 million but <$10M LCC

Project Type Project Manager Program Manager MDAA or Mission Support Office Official-in-Charge CIO OCE & OSMA Approval Authority for Waivers with Dissent
IT R A I   
I   MDAA or Mission Support Office Official-in-Charge   
OMSI R A I   A* MDAA or Mission Support Office Official-in-Charge

R = Recommends A = Approves I = Informed

*If the project is implemented at a Center, Center level SMA Approval is required.

Table 6-5 Waiver Approval for Programs and Projects < $1 million LCC

6.2.4 Waivers to requirements in NPRs referenced in this NPR may be granted according to the process established by the NPR's Responsible Office.

NPR 7120.7 Waiver Form



| TOC | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | ALL |
 
| NODIS Library | Program Formulation(7000s) | Search |

DISTRIBUTION:
NODIS


This Document is Obsolete and Is No Longer Used.
Check the NODIS Library to access the current version:
http://nodis3.gsfc.nasa.gov