NASA Procedures and Guidelines |
|||||
This Document is Obsolete and Is No Longer Used.
|
|||||
|
|||||
|
|
||||
| TOC | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | ALL | |
6.1.1 There are defined program and project management products (and their maturities) expected to be completed before each KDP. These products include documented project plans, design information, technical analyses, project metrics, and documentation of independent assessments. Program and project managers assemble this information in an orderly manner for presentation and discussion at the reviews prior to the KDPs.
Table 6-1 lists the gate products required for programs and describes their required maturity by KDP and major program review. Table 6-2 lists the gate products required for IT and OMSI projects and describes their required maturity by KDP and major project review. Products marked as "Updated" must be analyzed by the program or project, and any required changes made prior to the KDP. The date markings of the documents and their revision histories must be changed to indicate that the analysis occurred, even if changes to the content of the documents were not needed.
NPR 7120.7 Program Gate Products | ||||
---|---|---|---|---|
Products | Formulation | Implementation | ||
KDP I | KDP II | KDP III | KDP n | |
FAD | Approved | |||
PCA | Approved | Updated | Updated | Updated |
Program Plan | Approved | Updated | Updated | Updated |
Interagency and International Agreements | Approved | |||
PCDR Products | Final | |||
PIR Products | Final | Final | Final |
Table 6-1 Program Gate Products Maturity Matrix
6.2.1 Waivers to requirements in this NPR may be granted by the officials shown in Tables 6-3, 6-4, and 6.5. Waivers are used to adapt the requirements to the scope and scale of Information Technology and Institutional Infrastructure programs and projects.
6.2.2 Waivers with dissent are reviewed and dispositioned by the NASA Deputy Administrator for programs and projects with a life-cycle cost equal to or greater than 10 million dollars and by the OCE, cognizant MDAA or Mission Support Office Official-in- Charge for all other programs and projects, depending on the life-cycle cost.
NPR 7120.7 Project Gate Products | |||||||
---|---|---|---|---|---|---|---|
Products | Pre-Phase A | Phase A | Phase B | Phase C | Phase D | Phase E | Phase F |
KDP A | KDP B | KDP C | KDP D | KDP E | KDP F | ||
SCR | SRR | PDR | CDR | TRR/ ORR | PCR | ||
Project Planning, Cost, Schedule, and Communication Products | |||||||
1. FAD | Approved | Approved (if there was no Pre-Phase A) | |||||
2. Program Requirements on the Project | Preliminary | Baseline | Updated | ||||
3. Work Agreements for next phase | Baseline | Baseline | Baseline | Baseline | Baseline | Baseline | |
4. Integrated Baseline | Preliminary | Baseline | |||||
5. Governing Body Review products | Final | Final | Final | Final | Final | Final | |
6. Software Development/Management Plan as required by NPR 7150.2, NASA Software Engineering Requirements (IT Projects only) | Preliminary | Final | |||||
7. Project Plan (refer to Chapter 4; Appendix F provides a template; individual sub-plans can be stand-alone documents) | Preliminary | Baseline | Updated | Updated | |||
Project Technical Products | |||||||
1. System Concept | Preliminary | Baseline | |||||
2.Information/System Security Categorization (IT Projects Only) | Preliminary | Baseline | |||||
3. System Level Requirements | Preliminary | Baseline | |||||
4. System Technical Architecture | Preliminary | Baseline | |||||
5. Operations Concept | Preliminary | Baseline | |||||
6. Preliminary Design | Baseline | ||||||
7. Detailed Design | Baseline | ||||||
8. Test Plan, Test Procedures, and Test Cases | Baseline | ||||||
9. Training Plan and Training Materials | Preliminary | Baseline | Updated | ||||
10. As-built and As-deployed Hardware and Software Documentation | Baseline | ||||||
11. Operations Handbook | Preliminary | Baseline | |||||
12. Project Completion Report | Final | ||||||
13. Decommissioning Plan | Final | ||||||
IT Project Certification Products (IT Projects Only) | |||||||
Products | Pre-Phase A | Phase A | Phase B | Phase C | Phase D | Phase E | Phase F |
KDP A | KDP B | KDP C | KDP D | KDP E | KDP F | ||
1. Certification that project is ready to transition to the next phase | Final | Final | Final | Final | Final | Final | |
2. IT Security Certification and Accreditation of System | Initial | Triennial renewal |
Table 6-2 Project Gate Products Maturity Matrix (continued)
Note: The products shown in Table 6-2 are a minimal set. Depending on the nature of the project, other products (e.g., a Disaster Recovery Plan) called out in other policy documents may be required.
6.2.3 Requests for waivers to requirements in this NPR are documented and submitted for approval using the NPR 7120.7 Waiver Form. Prior to the KPD I for programs and KDP B and KDP C for projects, these requests may be documented and attached to a single waiver to assure proper routing and control. Waivers impacting formulation or requiring long lead time may be submitted individually early in formulation. Following KDP I for programs and KDP C for projects, waivers must be submitted individually to the appropriate authorities.
Project Type | Project Manager | Program Manager | MDAA or Mission Support Office Official-in- Charge | CIO | OCE & OSMA | Approval Authority for Waivers with Dissent |
---|---|---|---|---|---|---|
IT | R | A | A | A | A | NASA Deputy Administrator |
OMSI | R | A | A | A | NASA Deputy Administrator |
R = Recommends A = Approves I = Informed
Table 6-3 Waiver Approval for Programs and Projects >= $10 million Life-Cycle Cost (LCC)
Project Type | Project Manager | Program Manager | MDAA or Mission Support Office Official- in-Charge | CIO | OCE & OSMA | Approval Authority for Waivers with Dissent |
---|---|---|---|---|---|---|
IT | R | A | A | A | I | OCE |
OMSI | R | A | A | A* | OCE |
R = Recommends A = Approves I = Informed
*If the project is implemented at a Center, Center level SMA Approval is required.
Table 6-4 Waiver Approval for Programs and Projects >= $1 million but <$10M LCC
Project Type | Project Manager | Program Manager | MDAA or Mission Support Office Official-in-Charge | CIO | OCE & OSMA | Approval Authority for Waivers with Dissent |
---|---|---|---|---|---|---|
IT | R | A | I | |||
I | MDAA or Mission Support Office Official-in-Charge | |||||
OMSI | R | A | I | A* | MDAA or Mission Support Office Official-in-Charge |
R = Recommends A = Approves I = Informed
*If the project is implemented at a Center, Center level SMA Approval is required.
Table 6-5 Waiver Approval for Programs and Projects < $1 million LCC
6.2.4 Waivers to requirements in NPRs referenced in this NPR may be granted according to the process established by the NPR's Responsible Office.
NPR 7120.7 Waiver Form
| TOC | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | ALL | |
| NODIS Library | Program Formulation(7000s) | Search | |