NASA Space Flight Program and Project Management Requirements

| TOC | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | Figure2-2 | ALL |


APPENDIX C. Formulation Authorization Document Template


C.1      Program FAD Title Page

Figure C-1 Program Formulation Authorization Document Title Page

Figure C-1 Program Formulation Authorization Document Title Page

C.2      Project FAD Title Page

Figure C-2 Project Formulation Authorization Document Title Page

Figure C-2 Project Formulation Authorization Document Title Page

C.3.     Program/Project FAD Template

PROGRAM/PROJECT

FORMULATION AUTHORIZATION DOCUMENT
(PROGRAM/PROJECT TITLE)

1.0          PURPOSE

Describe the purpose of the program/project.  The program/project purpose must have clear traceability from the goals and objectives in the Mission Directorate Strategies or Program Plan (as applicable).  This need is independent of any particular technological solution and is stated in terms of functional capabilities.

2.0          AUTHORITY

Describe the NASA organizational structure for managing the formulation process from the MDAA  to the NASA Center program/project managers, as applicable.  Include lines of authority, coordination, and reporting.

3.0          PROGRAM / PROJECT GOALS AND OBJECTIVES

Describe the level or scope of work, goals, and objectives to be accomplished in the formulation phase, formulation cost targets and constraints, the time available, and any other constraints.

4.0          INTERNAL PARTICIPANTS

Identify Mission Directorates, Mission Support Offices, and Centers to be involved in the activity, their scope of work, and any known constraints related to their efforts (e.g., the program/project must be co-funded by a different Mission Directorate).

5.0          EXTERNAL PARTICIPANTS

Identify participation external to NASA to be involved in the activity, their scope of work, and any known constraints related to their efforts (e.g., the program/project must be co-funded by the external participant).

6.0          FUNDING

Identify, by fiscal year, the funding that will be committed for formulation.

7.0          REVIEWS

Describe the reviews according to the space flight program and project reviews tables in   Chapter 2, required during the formulation phase.



| TOC | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | Figure2-2 | ALL |
 
| NODIS Library | Program Formulation(7000s) | Search |

DISTRIBUTION:
NODIS


This Document is Obsolete and Is No Longer Used.
Check the NODIS Library to access the current version:
http://nodis3.gsfc.nasa.gov