a. "Initial" is applied to products that are continuously developed and updated as the program or project matures.
b. "Final" is applied to products that are expected to exist in this final form, e.g., minutes and final reports.
c. "Summary" is applied to products that synthesize the results of work accomplished.
d. "Plan" is applied to products that capture work that is planned to be performed in the following phases.
e. "Update" is applied to products that are expected to evolve as the formulation and implementation processes evolve. Only expected updates are indicated. However, any document may be updated, as needed.
Products | Formulation | Implementation | |
---|---|---|---|
KDP I1 | KDP I1 | ||
SRR | SDR | PIR | |
1. FAD | Baseline | ||
2. PCA | Preliminary | Baseline | |
3. Program Plan | Preliminary | Baseline | Update |
3.a. Mission Directorate requirements and constraints | Baseline | Update | |
3.b. Traceability of program-level requirements on projects to the Agency strategic goals and Mission Directorate requirements and constraints | Preliminary | Baseline | |
3.c. Documentation of driving ground rules and assumptions on the program | Preliminary | Baseline | |
4. Interagency and international agreements | Preliminary | Baseline | |
5. ASM minutes | Final | ||
6. Risk mitigation plans and resources for significant risks | Initial | Update | Update |
7. Documented Cost and Schedule Baselines | Preliminary | Baseline | Update |
8. Documentation of Basis of Estimate (cost and schedule) | Preliminary | Baseline | Update |
9. Documentation of performance against plan/baseline, including status/closure of formal actions from previous KDP. | Summary | Summary | Summary |
10. Plans for work to be accomplished during Implementation | Plan | Plan | |
Program Plan Control Plans2 | |||
1. Technical, Schedule, and Cost Control Plan | Preliminary | Baseline | |
2. Safety and Mission Assurance Plan | Preliminary | Baseline | |
3. Risk Management Plan | Preliminary | Baseline | |
4. Acquisition Plan | Preliminary | Baseline | |
5. Technology Development Plan | Preliminary | Baseline | |
6. Systems Engineering Management Plan | Preliminary | Baseline | |
7. Review Plan | Baseline | Update | |
8. Environmental Management Plan | Baseline | ||
9. Configuration Management Plan | Baseline | ||
10. Security Plan | Baseline | ||
11. Technology Transfer (formerly Export) Control Plan | Baseline | ||
12. Communications Plan | Baseline | ||
13. Knowledge Management Plan | Preliminary | Baseline |
2 Requirements for and scope of control plans will depend on scope of program. As noted in the template, control plans may be a part of the basic Program Plan.
Table I-2 Tightly Coupled Program Milestone Products Maturity Matrix
Products | Formulation | Implementation | ||||||
---|---|---|---|---|---|---|---|---|
KDP 0 | KDP I | KDP II | KDP III | KDP n | ||||
SRR | SDR | PDR | CDR | SIR | ORR | MRR/FRR | DR | |
1. FAD | Baseline | |||||||
2. PCA | Preliminary | Baseline | ||||||
3. Program Plan | Preliminary | Baseline | Update | Update | Update | Update | Update | Update |
3.a. Mission Directorate requirements and constraints | Baseline | Update | Update | |||||
3.b. Traceability of program-level requirements on projects to the Agency strategic goals and Mission Directorate requirements and constraints | Preliminary | Baseline | Update | |||||
3.c. Documentation of driving ground rules and assumptions on the program | Preliminary | Baseline | Update | Update | Update | |||
4. Interagency and international agreements | Preliminary | Baseline | Update | |||||
5. ASM minutes | Final | |||||||
6. Risk mitigation plans and resources for significant risks | Initial | Update | Update | Update | Update | Update | Update | Update |
7. Documented Cost and Schedule Baselines | Preliminary | Preliminary | Baseline | Update | Update | Update | Update | Update |
8. Documentation of Basis of Estimate (cost and schedule) | Preliminary | Preliminary | Baseline | Update | Update | Update | Update | Update |
9. Confidence Level(s) and supporting documentation | Preliminary cost confidence level and preliminary schedule confidence level | Baseline Joint Cost and Schedule Confidence Level |
||||||
10. Shared Infrastructure1, Staffing, and Scarce Material Requirements and Plans | Initial | Update | Update | Update | ||||
11. Documentation of performance against plan/baseline, including status/closure of formal actions from previous KDP | Summary | Summary | Summary | Summary | Summary | Summary | Summary | |
12. Plans for work to be accomplished during next life-cycle phase | Plan | Plan | Plan | Plan | Plan |
Table I-3 Tightly Coupled Program Plan Control Plans Maturity Matrix
NPR 7120.5 Program Plan Control Plans (See template in Appendix G for control plan details.) |
Formulation | Implementation | ||||||
---|---|---|---|---|---|---|---|---|
KDP 0 | KDP I | KDP II | KDP III | KDP n | ||||
SRR | SDR | PDR | CDR | SIR | ORR | MRR/FRR | DR | |
1. Technical, Schedule, and Cost Control Plan | Preliminary | Baseline | Update | |||||
2. Safety and Mission Assurance Plan | Preliminary | Baseline | Update | Update | Update (SMSR) | |||
3. Risk Management Plan | Preliminary | Baseline | Update | |||||
4. Acquisition Plan | Preliminary Strategy | Baseline | Update | |||||
5. Technology Development Plan | Preliminary | Baseline | Update | |||||
6. Systems Engineering Management Plan | Preliminary | Baseline | ||||||
7. Verification and Validation Plan | Preliminary | Baseline | Update | Update | ||||
8. Information Technology Plan | Preliminary | Baseline | Update | |||||
9. Review Plan1 | Baseline | Update | Update | |||||
10. Missions Operations Plan | Preliminary | Baseline | Update | |||||
11. Environmental Management Plan | Preliminary | Baseline | Update | |||||
12. Integrated Logistics Support Plan | Preliminary | Baseline | Update | |||||
13. Science Data Management Plan | Preliminary | Baseline | Update | |||||
14. Configuration Management Plan2 | Preliminary | Baseline | Update | |||||
15. Security Plan | Preliminary | Baseline | ||||||
16. Technology Transfer (formerly Export) Control Plan | Preliminary | Baseline | Update | |||||
17. Communications Plan | Preliminary | Baseline | Update | Update | ||||
18. Knowledge Management Plan | Preliminary | Baseline | Update |
|
||||
19. Human Rating Certification Package | Initial | Update | Update | Update | Update | Approve Certification |
|
2 Software and hardware configuration management may be preliminary at SRR and updated at SDR.
Table I-4 Project Milestone Products Maturity Matrix
Products | Pre-Phase A KDP A |
Phase A KDP B |
Phase B KDP C |
Phase C KDP D |
Phase D KDP E |
Phase E KDP F |
Phase F | |||
---|---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/ FRR |
DR | DRR | |
Headquarters and Program Products1 | ||||||||||
1. FAD | Baseline | |||||||||
2. Program Plan | Baseline | |||||||||
2.a. Applicable Agency strategic goals | Baseline | Update | Update | |||||||
2.b. Documentation of program-level requirements and constraints on the project (from the Program Plan) and stakeholder expectations, including mission objectives/goals and mission success criteria | Preliminary | Baseline | Update | Update | ||||||
2.c. Documentation of driving mission, technical, and programmatic ground rules and assumptions | Preliminary | Preliminary | Baseline | Update | Update | Update | ||||
3. Partnerships and interagency and international agreements | Preliminary | Update | Baseline U.S. partnerships and agreements | Baseline international agreements | ||||||
4. ASM minutes | Final | |||||||||
5. NEPA compliance documentation per NPR 8580.1 | Final documentation per NPR 8580.1 | |||||||||
6. Mishap Preparedness and Contingency Plan | Preliminary | Update | Baseline (SMSR) | Update | Update | |||||
Project Technical Products2 | ||||||||||
1. Concept Documentation | Approve | Update | Update | Update | ||||||
2. Mission, Spacecraft, Ground, and Payload Architectures | Preliminary mission and spacecraft architecture(s) with key drivers | Baseline mission and spacecraft architecture, preliminary ground and payload architectures. Classify payload(s) by risk per NPR 8705.4. | Update mission and spacecraft architecture, baseline ground and payload architectures | Update mission, spacecraft, ground and payload architectures | ||||||
3. Project-Level, System, and Subsystem Requirements | Preliminary project-level requirements | Baseline project-level and system-level requirements | Update Project-level and system-level requirements, Preliminary subsystem requirements | Update project-level and system-level requirements. Baseline subsystem requirements | ||||||
4. Design Documentation | Preliminary | Baseline Preliminary Design | Baseline Detailed Design | Update | Baseline As-built hardware and software | |||||
5. Operations Concept | Preliminary | Preliminary | Preliminary | Baseline | ||||||
6. Technology Readiness Assessment Documentation | Initial | Update | Update | Update | Update | |||||
7. Engineering Development Assessment Documentation | Initial | Update | Update | Update | ||||||
8. Heritage Assessment Documentation | Initial | Update | Update | Update | ||||||
9. Safety Data Packages [Baseline at CDR] [per NPRs 8715.3, 8735.1, and 8735.2] | Preliminary |
Baseline |
Update |
Update |
Update |
|||||
10. ELV Payload Safety Process Deliverables | Preliminary | Preliminary | Baseline | |||||||
11. Verification and Validation Report | Preliminary | Baseline | ||||||||
12. Operations Handbook | Preliminary | Baseline | Update | |||||||
13. Orbital Debris Assessment per NPR 8715.6 | Preliminary Assessment | Preliminary design ODAR | Detailed design ODAR | Final ODAR (SMSR) | ||||||
14. End of Mission Plans per NPR 8715.6/NASA-STD 8719.14, App B | Baseline End of Mission Plan (SMSR) | Update EOMP annually | Update EOMP | |||||||
15. Mission Report | Final | |||||||||
Project Management, Planning, and Control Products | ||||||||||
1. Formulation Agreement | Baseline for Phase A; Preliminary for Phase B | Baseline for Phase B | ||||||||
2. Project Plan | Preliminary | Baseline | ||||||||
3. Plans for work to be accomplished during next Implementation life-cycle phase | Baseline for Phase C | Baseline for Phase D | Baseline for Phase E | Baseline for Phase F | ||||||
4. Documentation of performance against Formulation Agreement (see #1 above) or against plans for work to be accomplished during Implementation life-cycle phase (see #3 above), including performance against baselines and status/closure of formal actions from previous KDP | Summary | Summary | Summary | Summary | Summary | Summary | Summary | Summary | ||
5.Project Baselines | Preliminary | Baseline | Update | Update | Update | Update | ||||
5.a. Top technical, cost, schedule and safety risks, risk mitigation plans, and associated resources | Initial | Update | Update | Update | Update | Update | Update | Update | Update | Update |
5.b. Staffing requirements and plans | Initial | Update | Update | Update | Update | Update | ||||
5.c. Infrastructure requirements and plans, business case analysis for infrastructure Capitalization Determination Form (CDF) (NASA Form 1739), per NPR 9250.1 |
Initial | Update | Update |
Update |
Update | |||||
5.d. Schedule | Risk informed at project level with preliminary Phase D completion ranges | Risk informed at system level with preliminary Phase D completion ranges | Risk informed at subsystem level with preliminary Phase D completion ranges. Preliminary Integrated Master Schedule | Risk informed and cost- or resource-loaded. Baseline Integrated Master Schedule | Update IMS | Update IMS | Update IMS | |||
5.e. Cost Estimate (Risk-Informed or Schedule-Adjusted Depending on Phase) | Preliminary Range estimate | Update | Risk-informed schedule-adjusted range estimate | Risk-informed and schedule-adjusted Baseline | Update | Update | Update | Update | Update | Update |
5.f. Basis of Estimate (cost and schedule) | Initial (for range) | Update (for range) | Update (for range) | Update for cost and schedule estimate | Update | Update | Update | Update | Update | Update |
5.g. Confidence Level(s) and supporting documentation | Preliminary cost confidence level and preliminary schedule confidence level | Baseline Joint Cost and Schedule Confidence Level |
||||||||
5.h. External Cost and Schedule Commitments | Preliminary for ranges | Baseline | ||||||||
5.i. CADRe | Baseline | Update | Update | Update | Update3 | Update | ||||
6. Decommissioning/Disposal Plan | Baseline | Update Disposal portions |
2 These document the work of the key technical activities performed in the associated phases.
3The CADRe for MRR/FRR is considered the "Launch CADRe" to be completed after the launch.
Table I-5 Project Plan Control Plans Maturity Matrix
NPR 7120.5 Project Plan Control Plans (See template in Appendix H for control plan details) |
Pre-Phase A | Phase A KDP B |
Phase B KDP C |
Phase C KDP D |
Phase D KDP E |
Phase E KDP F |
|||
---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/ FRR | DR | |
1. Technical, Schedule, and Cost Control Plan | Approach for managing schedule and cost during Phase A1 | Preliminary | Baseline | Update | |||||
2. Safety and Mission Assurance Plan | Baseline | Update | Update | Update | Update (SMSR) | Update | |||
3. Risk Management Plan | Approach for managing risks during Phase A1 | Baseline | Update | Update | |||||
4. Acquisition Plan | Preliminary Strategy | Baseline | Update | Update | |||||
5. Technology Development Plan (may be part of Formulation Agreement) | Baseline | Update | Update | Update | |||||
6. Systems Engineering Management Plan | Preliminary | Baseline | Update | Update | |||||
7. Information Technology Plan | Preliminary | Baseline | Update | ||||||
8. Software Management Plan(s) | Preliminary | Baseline | Update | ||||||
9. Verification and Validation Plan | Preliminary Approach2 | Preliminary | Baseline | Update | Update | ||||
10. Review Plan | Preliminary | Baseline | Update | Update | |||||
11. Mission Operations Plan | Preliminary | Baseline | Update | ||||||
12. Environmental Management Plan | Baseline | ||||||||
13. Integrated Logistics Support Plan | Approach for managing logistics2 | Preliminary | Preliminary | Baseline | Update | ||||
14. Science Data Management Plan | Preliminary | Baseline | Update | ||||||
15. Integration Plan | Preliminary approach2 | Preliminary | Baseline | Update | |||||
16. Configuration Management Plan | Baseline | Update | Update | ||||||
17. Security Plan | Preliminary | Baseline | Update annually | ||||||
18. Project Protection Plan | Preliminary | Baseline | Update | Update | Update | Update | Update annually | ||
19. Technology Transfer (formerly Export) Control Plan | Preliminary | Baseline | Update | ||||||
20. Knowledge Management Plan | Approach for managing during Phase A1 | Preliminary | Baseline | Update | |||||
21. Human Rating Certification Package | Preliminary approach 2 | Initial | Update | Update | Update | Update | Approve Certification | ||
22. Planetary Protection Plan | Planetary Protection Certification (if required) | Baseline | |||||||
23. Nuclear Safety Launch Approval Plan | Baseline (mission has nuclear materials) | ||||||||
24. Range Safety Risk Management Process Documentation | Preliminary | Preliminary | Baseline | ||||||
25. Communications Plan | Preliminary | Baseline | Update | Update |
2 Not the Plan, but documentation of considerations that might impact the cost and schedule baselines. May be documented in MCR briefing package.
Table I-6 Single-Project Program Milestone Products Maturity Matrix
Products | Pre-Phase A KDP A |
Phase A KDP B |
Phase B KDP C |
Phase C KDP D |
Phase D KDP E |
Phase E KDP F |
Phase F | |||
---|---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/FRR | DR | DRR | |
Headquarters Products1 | ||||||||||
1. FAD | Baseline | |||||||||
2. PCA | Preliminary | Baseline | ||||||||
3. Traceability of Agency strategic goals and Mission Directorate requirements and constraints to program/project-level requirements and constraints. | Preliminary | Baseline | Update | Update | ||||||
4. Documentation of driving mission, technical, and programmatic ground rules and assumptions | Preliminary | Preliminary | Baseline | Update | Update | Update | ||||
5. Partnerships and inter-agency and international agreements | Preliminary | Update | Baseline U.S. partnerships and agreements | Baseline international agreements | ||||||
6. ASM minutes | Final | |||||||||
7. NEPA compliance documentation per NPR 8580.1 | Final documentation per NPR 8580.1 | |||||||||
8. Mishap Preparedness and Contingency Plan | Preliminary | Update | Baseline (SMSR) | Update | Update | |||||
Single-Project Program Technical Products2 | ||||||||||
1. Concept Documentation | Approve | Update | Update | Update | ||||||
2. Mission, Spacecraft, Ground, and Payload Architectures | Preliminary mission and spacecraft architecture(s) with key drivers | Baseline mission and spacecraft architecture, preliminary ground and payload architectures. Classify payload(s) by risk per NPR 8705.4. | Update mission and spacecraft architecture, baseline ground and payload architectures | Update mission, spacecraft, ground, and payload architectures | ||||||
3. Project-Level, System, and Subsystem Requirements | Preliminary project-level requirements | Baseline project-level and system-level requirements | Update Project-level and system-level requirements, Preliminary subsystem requirements | Update project-level and system-level requirements. Baseline subsystem requirements | ||||||
4. Design Documentation | Preliminary | Baseline Preliminary Design | Baseline Detailed Design | Update | Baseline as-built hardware and software | |||||
5. Operations Concept | Preliminary | Preliminary | Preliminary | Baseline | ||||||
6. Technology Readiness Assessment Documentation | Initial | Update | Update | Update | Update | |||||
7. Engineering Development Assessment Documentation | Initial | Update | Update | Update | ||||||
8. Heritage Assessment Documentation | Initial | Update | Update | Update | ||||||
9. Safety Data Packages [Baseline at CDR] | Preliminary |
Baseline |
Update |
Update |
Update |
|||||
10. ELV Payload Safety Process Deliverables | Preliminary | Preliminary | Baseline | |||||||
11. Verification and Validation Report | Preliminary | Baseline | ||||||||
12. Operations Handbook | Preliminary | Baseline | Update | |||||||
13. Orbital Debris Assessment per NPR 8715.6 | Preliminary Assessment | Preliminary design ODAR | Detailed design ODAR | Final ODAR (SMSR) | ||||||
14. End of Mission Plans per NPR 8715.6/NASA-STD 8719.14, App B | Baseline End of Mission Plan (SMSR) | Update EOMP annually | Update EOMP | |||||||
15. Mission Report | Final | |||||||||
Single-Project Program Management, Planning, and Control Products | ||||||||||
1. Formulation Agreement | Baseline for Phase A; Preliminary for Phase B | Baseline for Phase B | ||||||||
2. Program Plan3 | Preliminary | Baseline | ||||||||
3. Project Plan3 | Preliminary | Baseline | ||||||||
4. Plans for work to be accomplished during next Implementation life-cycle phase | Baseline for Phase C | Baseline for Phase D | Baseline for Phase E | Baseline for Phase F | ||||||
5. Documentation of performance against Formulation Agreement (see #1 above) or against plans for work to be accomplished during Implementation life-cycle phase (see #3 above), including performance against baselines and status/closure of formal actions from previous KDP | Summary | Summary | Summary | Summary | Summary | Summary | Summary | Summary | ||
6.Project Baselines | Preliminary | Baseline | Update | Update | Update | Update | ||||
6.a. Top technical, cost, schedule and safety risks, risk mitigation plans, and associated resources | Initial | Update | Update | Update | Update | Update | Update | Update | Update | Update |
6.b. Staffing requirements and plans | Initial | Update | Update | Update | Update | Update | ||||
6.c. Infrastructure requirements and plans, business case analysis for infrastructure Capitalization Determination Form (CDF) (NASA Form 1739), per NPR 9250.1 |
Initial | Update | Update |
Update |
Update | |||||
6.d. Schedule | Risk informed at project level with preliminary Phase D completion ranges | Risk informed at system level with preliminary Phase D completion ranges | Risk informed at subsystem level with preliminary Phase D completion ranges. Preliminary Integrated Master Schedule | Risk informed and cost- or resource-loaded. Baseline Integrated Master Schedule | Update IMS | Update IMS | Update IMS | |||
6.e. Cost Estimate (Risk-Informed or Schedule-Adjusted Depending on Phase) | Preliminary Range estimate | Update | Risk-informed schedule-adjusted range estimate | Risk-informed and schedule-adjusted baseline | Update | Update | Update | Update | Update | Update |
6.f. Basis of Estimate (cost and schedule) | Initial (for range) | Update (for range) | Update (for range) | Update for cost and schedule estimate | Update | Update | Update | Update | Update | Update |
6.g. Confidence Level(s) and supporting documentation | Preliminary cost confidence level and preliminary schedule confidence level | Baseline Joint Cost and Schedule Confidence Level |
||||||||
6.h. External Cost and Schedule Commitments | Preliminary for ranges | Baseline | ||||||||
6.i. CADRe | Baseline | Update | Update | Update | Update4 | Update | ||||
7. Decommissioning/ Disposal Plan | Baseline | Update disposal portions |
2 These document the work of the key technical activities performed in the associated phases.
3 The program and project plans may be combined with the approval of the MDAA.
4The CADRe for MRR/FRR is considered the "Launch CADRe" to be completed after the launch.
Table I-7 Single-Project Program Plan Control Plans Maturity Matrix
NPR 7120.5 Program and Project Plan Control Plans (See template in Appendices G and H for control plan details) | Pre-Phase A | Phase A KDP B |
Phase B KDP C |
Phase C KDP D |
Phase D KDP E |
Phase E KDP F |
|||
---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/ FRR | DR | |
1. Technical, Schedule, and Cost Control Plan | Approach for managing schedule and cost during Phase A1 | Preliminary | Baseline | Update | |||||
2. Safety and Mission Assurance Plan | Baseline | Update | Update | Update | Update (SMSR) | Update | |||
3. Risk Management Plan | Approach for managing risks during Phase A1 | Baseline | Update | Update | |||||
4. Acquisition Plan | Preliminary Strategy | Baseline | Update | Update | |||||
5. Technology Development Plan (may be part of Formulation Agreement) | Baseline | Update | Update | Update | |||||
6. Systems Engineering Management Plan | Preliminary | Baseline | Update | Update | |||||
7. Information Technology Plan | Preliminary | Baseline | Update | ||||||
8. Software Management Plan(s) | Preliminary | Baseline | Update | ||||||
9. Verification and Validation Plan | Preliminary Approach2 | Preliminary | Baseline | Update | Update | ||||
10. Review Plan | Preliminary | Baseline | Update | Update | |||||
11. Mission Operations Plan | Preliminary | Baseline | Update | ||||||
12. Environmental Management Plan | Baseline | ||||||||
13. Integrated Logistics Support Plan | Approach for managing logistics2 | Preliminary | Preliminary | Baseline | Update | ||||
14. Science Data Management Plan | Preliminary | Baseline | Update | ||||||
15. Integration Plan | Preliminary approach2 | Preliminary | Baseline | Update | |||||
16. Configuration Management Plan | Baseline | Update | Update | ||||||
17. Security Plan | Preliminary | Baseline | Update annually | ||||||
18. Project Protection Plan | Preliminary | Baseline | Update | Update | Update | Update | Update annually | ||
19. Technology Transfer (formerly Export) Control Plan | Preliminary | Baseline | Update | ||||||
20. Knowledge Management Plan | Approach for managing during Phase A1 | Preliminary | Baseline | Update | |||||
21. Human Rating Certification Package | Preliminary approach2 | Initial | Update | Update | Update | Update | Approve Certification | ||
22. Planetary Protection Plan | Planetary Protection Certification (if required) | Baseline | |||||||
23. Nuclear Safety Launch Approval Plan | Baseline (mission has nuclear materials) | ||||||||
24. Range Safety Risk Management Process Documentation | Preliminary | Preliminary | Baseline | ||||||
26. Communications Plan | Preliminary | Baseline | Update | Update |
2 Not the Plan, but documentation of considerations that might impact the cost and schedule baselines. May be documented in MCR briefing package.
| TOC | ChangeLog | Preface | Chapter1 | Chapter2 | Chapter3 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | ALL | |
| NODIS Library | Program Formulation(7000s) | Search | |