(To be used in concert with Chapter 6. Demolition/Deconstruction)
Item and Chapter 6 Reference | Description | Other Reference Requirements | Notes | Lead Time Before Demolition (Months) |
---|---|---|---|---|
Sustainment Plan- Section 6.3.3(f) | Determine protection and maintenance requirements (safety, property, security, environmental) between facility deactivation and demolition. | Complete as part of decommissioning. | ||
Evaluation of alternatives and determination to demolish (HUD Determination) - Section 6.5.1.1 | RPAO completes the Title V document for candidate properties and submits to FRED who interacts with HUD on behalf of the Agency. | NPR 8800.15, Chapter 7 Disposition of Real Property. | Evaluate disposal alternatives such as transfer to another agency or adaptive reuse (42 U.S.C. ยง 11301 et seq. screening). | 12 - 24 |
Evaluation of alternatives, completion of the NHPA Section 106 process - Section 6.5.1.2 | Determine historic eligibility, conduct alternatives analysis for historic properties, complete NHPA Section 106 review process (including mitigation), as appropriate, in accordance with the executed agreement document. | NPR 8580.1, Implementing the National Environmental Policy. Also, NPR 8800.15, Chapter 7 Disposition of Real Property. | If eligible, consultation with SHPO and other stakeholders may be required. | 12 - 24 (prior to execution of demolition) |
Authority to Dispose/Demolis h - Section 6.5.1.3 | Submit a letter, signed by the Center Director or designee, requesting authority to proceed with the demolition. | NPR 8800.15, Chapter 7 Disposition of Real Property. | This authority is separate from the request to include the facility in the demolition program as part of the PPBES process. | |
Request inclusion into the Demolition Program - Section 6.6 | Request funding for demolition of the facility as part of the PPBES process. | Annual PPBES Guidance; NPR 8800.15, Chapter 7 Disposition of Real Property. | Identify earliest demolition date and any schedule constraints. | 24 - 36 |
Funding NASA Interagency Purchase Request (NIPR) to the USACE - Section 6.7.1 | Transfer of NASA Demolition Program funding to the U.S. Army Corps of Engineers (USACE). | Identify earliest demolition date and any schedule constraints. | This is required only if Center's use NASA's centralized USACE demolition execution capability. | |
Compliance with NEPA - Section 6.7.4 | Complete Record of Environmental Planning and Environmental Checklist (additional actions may be required). | NPR 8580.1, Implementing the National Environmental Policy. NPR 8800.15, Chapter 7 Disposition of Real Property. | 24 | |
Environmental Checklist - Section 6.7.4.2 | Identify hazardous substances to be removed as part of demolition (asbestos, lead) and prior to demolition (chemical containers). | NPR 8800.15, Chapter 7 Disposition of Real Property. | ||
Salvage Material Inventory/ Diversion Plan - Section 6.7.6 | Estimate the types and amount of materials that could have salvage value as recycled material or reuse. Evaluate how to minimize waste to landfill. | NPR 8800.15, Chapter 7 Disposition of Real Property. | During final design. | 6 - 12 |
Clear the building of non-collateral equipment and debris - Section 6.7.6 | Ensure that any personal property is properly disposed of separate from facility demolition. | Coordinate with the Center's Property Disposal Officer. | 6 - 12 | |
Pollution Prevention and Hazardous Material Abatement Plan - Section 6.7.6 | Identify potential environmental risks associated with the work such as hazardous waste disposal, run off/erosion, underground storage tank systems, wetlands, and floodplains. Determine required remediation. | NPR 8800.15, Chapter 7 - Disposition of Real Property. | Complete as part of building decommissioning. | |
Personal Property Reuse Plan - Section 6.7.8 | Identify equipment, property, and artifacts for reuse by the Government or disposal by other means. | NPR 8800.15, Chapter 7 Disposition of Real Property. | Coordinate with the CRM, Property Disposal Officer, Program POCs, and any other special interest groups early in the process. | 12 - 24 |
Evaluate infrastructure impact - Section 6.7.9 | Look at impact to utilities, roads, other facilities, physical security, etc. | Demolition of a facility may remove either supply or demand of essential services, requiring modifications to associated systems. | 12 - 24 | |
Safety Baseline Survey - Section 6.7.10 | Identify potential safety hazards and concerns such as: a. Facility safety b. Fire protection c. Confined space entry d. Nuclear safety e. Radiation protection f. Explosives g. Pressurized systems | NPR 8800.15, Chapter 7 Disposition of Real Property. | Complete as part of decommissioning. | |
Communication Plan (No Section Reference) | Determine if a plan for communicating the content of the demolition project (and associated impacts) to the Center and the surrounding community is required. | During final design. | 6 - 12 |