Table C highlights NASA's steps in complying with Federal budget formulation requirements and provides a top-level schedule for the activities. The schedule below assumes NASA initiates the Planning Phase a full calendar year before a preliminary OMB Submit is completed (i.e. about two calendar years before the start of the budget year).
Note: Table C shows an ideal schedule, but actual timetables may vary. The development of performance reports and plans are managed separately and excluded from the schedule. Coordination between budget and performance occur throughout the process. Note that development of performance reports and plans are managed separately and not included in the schedule. Coordination between budget and performance should be considered as occurring throughout the process.
Action | Timeframe (General) |
---|---|
OCFO SID develops and releases SPG with guidance on initial budget marks and formulation. | December - February |
CAMs develop and release PRG for program and projects funded within their budget accounts. | February |
CAMs, with inputs from Centers and OHCM, conduct PAA to baseline budget estimates. CAMs identify within-account and institutional/cross-cutting issues for resolution and submit PAA reports. | March |
CAMS submit PAA and issues and present to the Administrator and other senior leaders. | May - June |
OCFO SID prepares a summary of issues and coordinates EC/SMC reviews for discussions on PAA issues. Senior leaders provide their recommendations. The EC conducts Agency Budget Review and makes Agency Budget Decisions. | June - July |
OCFO SID develops and releases PaIG based on EC decisions. | July-August |
CAMs update budgets in the budget formulation database and develop OMB Submit materials. | August |
CFO and OCFO BD develop Agency-level OMB Submit materials and update MAX A-11 and other Government-wide PBR formulation systems. | August - September |
CFO provides OMB Submit. CAMs support OMB Submit with briefings and responses to OMB questions. | September - November |
OMB considers proposed budgets and provides budget guidance and direction at the Agency and account levels (the passback process). NASA may appeal and provide additional justification to OMB. | September - December |
OMB considers appeals and provides decisions in a settlement document. | December |
OCFO BD initiates CJ production processes. | November - February |
CAMs finalize account budgets and develop justification materials. OCFO BD develops other required budget materials. | January - February |
OCFO BD updates Government-wide PBR formulation databases with updated budget estimates. | January |
OMB approves final budgets, all CJ content, and budget rollout materials. | January - February |
Office of Communications and OCFO lead budget rollout process planning with CAMs and senior leaders. | January - February |
Executive Office/President releases PBR. NASA releases CJ in accordance with guidance in OMB Circular A-11. | February |
NASA Administrator and other senior leaders appear before Congressional Committees to testify in support of the budget request. | February - Appropriation |
NASA Administrator and CAMs respond to Congressional questions for the record. OCFO BD tracks progress of appropriations markup and discussions. CAMs develop strategies and position accounts for actual appropriations. | February - Appropriation |
| TOC | ChangeLog | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | ALL | |
| NODIS Library | Financial Management(9000s) | Search | |
This document does not bind the public, except as authorized by law or as incorporated into a contract. This document is uncontrolled when printed. Check the NASA Online Directives Information System (NODIS) Library to verify that this is the correct version before use: https://nodis3.gsfc.nasa.gov.