Item | Description | Reference Requirement | Notes | Lead Time Before Demolition (Months) |
---|---|---|---|---|
Authority to dispose/ demolish | Submit a letter, signed by the Center Director or designee, requesting authority to proceed with the demolition. | NPR 8800.15B Chapter 8 | This authority is separate from the request to include the facility in the demolition program as part of the PPBE process. | |
Determination to demolish | NPR 8800.15B Chapter 8 | Evaluate disposal alternatives such as transfer to another agency or adaptive reuse (McKinney Act screening) | ||
Request inclusion in the demolition program | Request funding for demolition of the facility as part of the PPBE process. | Annual PPBE Guidance | Identify earliest demolition date and any schedule constraints. | 24 - 36 |
Compliance with NHPA | Determine historic eligibility, look at adaptive reuse, determine mitigating measures such as HABS/HAER | NPR 8580.1 | If eligible, SHPO consult may be required. | |
Environmental baseline survey | Identify hazardous substances to be removed as part of demolition (asbestos, lead) and prior to demolition (chemical containers) | NPR 8800.15B Chapter 8 | ||
Compliance with NEPA | Complete Record of Environmental Planning and Environmental Checklist (additional actions may be required) | NPR 8580.1 | 24 | |
Personal property reuse plan | Identify equipment, property and artifacts for reuse by the Government or disposal by other means | Bring in HPO's, property disposal officers, programs, and special interest groups early in the process | 12 - 24 | |
Salvage material inventory/ diversion plan | Estimate the types and amount of materials that could have salvage value as recycled material or reuse. Evaluate how to minimize waste to landfill. | NPR 8800.15B Chapter 8 | During design | 6 - 12 |
Clear the building of non-collateral equipment and debris | Ensure that any personal property is properly disposed of separate from facility demolition | Work with the property disposal officer | 6 - 12 | |
Evaluate infrastructure impact | Look at impact to: utilities, roads, other facilities, security | Demolition of a facility may remove either supply or demand of essential services, requiring modifications to associated systems. | 12 - 24 | |
Sustainment plan | Determine protection and maintenance requirements (safety, property, security, environmental) between facility deactivation and demolition | Complete as part of decommissioning | ||
Safety baseline survey | Identify potential safety hazards and concerns such as: a. Facility safety. b. Fire protection. c. Confined space entry. d. Nuclear safety. e. Radiation protection. f. Explosives. g. Pressurized systems. |
NPR 8800.15B Chapter 8 | Complete as part of decommissioning | |
Pollution prevention and abatement plan | Identify potential environmental risks associated with the work such as hazardous waste disposal, run off/erosion, underground storage tank systems, wetlands, and floodplains. Determine required remediation. | NPR 8800.15B Chapter 8 | Complete as part of decommissioning | |
Communication plan | Determine if a plan is needed to communicate to the Center and surrounding community information about the demolition and impacts. | During design | 6 - 12 |