Appendix E. Demolition Planning Checklist

Item Description Reference Requirement Notes Lead Time Before Demolition (Months)
Authority to dispose/ demolish Submit a letter, signed by the Center Director or designee, requesting authority to proceed with the demolition. NPR 8800.15B Chapter 8 This authority is separate from the request to include the facility in the demolition program as part of the PPBE process.
Determination to demolish NPR 8800.15B Chapter 8 Evaluate disposal alternatives such as transfer to another agency or adaptive reuse (McKinney Act screening)
Request inclusion in the demolition program Request funding for demolition of the facility as part of the PPBE process. Annual PPBE Guidance Identify earliest demolition date and any schedule constraints. 24 - 36
Compliance with NHPA Determine historic eligibility, look at adaptive reuse, determine mitigating measures such as HABS/HAER NPR 8580.1 If eligible, SHPO consult may be required.
Environmental baseline survey Identify hazardous substances to be removed as part of demolition (asbestos, lead) and prior to demolition (chemical containers) NPR 8800.15B Chapter 8
Compliance with NEPA Complete Record of Environmental Planning and Environmental Checklist (additional actions may be required) NPR 8580.1 24
Personal property reuse plan Identify equipment, property and artifacts for reuse by the Government or disposal by other means Bring in HPO's, property disposal officers, programs, and special interest groups early in the process 12 - 24
Salvage material inventory/ diversion plan Estimate the types and amount of materials that could have salvage value as recycled material or reuse. Evaluate how to minimize waste to landfill. NPR 8800.15B Chapter 8 During design 6 - 12
Clear the building of non-collateral equipment and debris Ensure that any personal property is properly disposed of separate from facility demolition Work with the property disposal officer 6 - 12
Evaluate infrastructure impact Look at impact to: utilities, roads, other facilities, security Demolition of a facility may remove either supply or demand of essential services, requiring modifications to associated systems. 12 - 24
Sustainment plan Determine protection and maintenance requirements (safety, property, security, environmental) between facility deactivation and demolition Complete as part of decommissioning
Safety baseline survey Identify potential safety hazards and concerns such as:

a. Facility safety.

b. Fire protection.

c. Confined space entry.

d. Nuclear safety.

e. Radiation protection.

f. Explosives.

g. Pressurized systems.
NPR 8800.15B Chapter 8 Complete as part of decommissioning
Pollution prevention and abatement plan Identify potential environmental risks associated with the work such as hazardous waste disposal, run off/erosion, underground storage tank systems, wetlands, and floodplains. Determine required remediation. NPR 8800.15B Chapter 8 Complete as part of decommissioning
Communication plan Determine if a plan is needed to communicate to the Center and surrounding community information about the demolition and impacts. During design 6 - 12


| TOC | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | ALL |
 
| NODIS Library | Program Management(8000s) | Search |

DISTRIBUTION:
NODIS


This Document is Obsolete and Is No Longer Used.
Check the NODIS Library to access the current version:
http://nodis3.gsfc.nasa.gov