NPR 7120.8A Effective Date: September 14, 2018 Expiration Date: September 14, 2028 |
| TOC | ChangeLog | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | AppendixK | AppendixL | AppendixM | ALL | |
|
|
|
1 |
05/26/2020 |
Changes related to the transition of the NPR responsible office from the Chief Engineer to the NASA AA and Chief Program Management Officer (CPMO) for management of the NPR on behalf of the NASA AA. |
2 |
09/13/2021 |
In para 5.3 change name of process from Dissenting Opinion Process to Formal Dissent Process; In Appendix A, update definitions in alignment with definitions in NPR 7120.5F; in Appendix G para 4.2, update example control plan list to include the Human System Integration approach; in Appendix K, replace section with pointer to newly published Technology Readiness Assessment Guide; and throughout document, change IT Security Plan to System Security Plan |
3 |
08/10/2023 |
Changes related to the transition of the NPR responsible office from the Chief Engineer to the NASA AA and Chief Program Management Officer (CPMO) for management of the NPR on behalf of the NASA AA. |
4 |
09/19/2023 |
Revalidated with 1400 compliant and administrative changes. |
5 |
10/27/2023 |
Updated Applicability statement to agree with NPR 7120.5. |
| TOC | ChangeLog | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | AppendixK | AppendixL | AppendixM | ALL | |
| NODIS Library | Program Formulation(7000s) | Search | |
This document does not bind the public, except as authorized by law or as incorporated into a contract. This document is uncontrolled when printed. Check the NASA Online Directives Information System (NODIS) Library to verify that this is the correct version before use: https://nodis3.gsfc.nasa.gov.