Chapter 1. Introduction

1.1 General

This NPR provides basic requirements and instructions to assist in preparation of Contractor Financial Management Reports (NASA Form 533 reports).

1.2 Purpose of the NASA Form 533 Reports

1.2.1 NASA Form 533 (NF 533) reports provide data necessary for:

a. Projecting costs and hours to ensure dollar and labor resources realistically support project and program schedules.

b. Evaluating contractors' actual cost and fee data in relation to negotiated contract value, estimated costs, and budget forecast data.

c. Planning, monitoring, and controlling project and program resources.

d. Accruing cost in NASA's accounting system resulting in liabilities reflected on the financial statements and providing program and functional management information. Cost is a financial measurement of resources used in accomplishing a specified purpose, such as performing a service, carrying out an activity, acquiring an asset, or completing a unit of work or project. NASA is required by law to use accrual accounting, which requires cost to be reported in the period in which benefits are received, without regard to time of payment. To facilitate this process, NASA requires its contractors to report accrued costs on NF 533 reports on cost type, price redetermination, and fixed-price incentive contracts.

1.3 Policy and Related Requirements

1.3.1 Agency policies and responsibilities governing the Contractor Financial Management Reporting System are set forth in NPD 9501.1.

1.3.2 NASA contractors are expected to submit financial management reports in which cost information is compatible with the technical and schedule reporting structure. The exact level and detail of these data are based upon NASA management requirements and the contractor's management system. When Earned Value Management System (EVMS) or other performance measurement system (PMS) and NF 533 reports are required under the contract, they shall reflect information that is consistent and generated from the same management information systems.

1.4 Contract Implementation

1.4.1 Contract implementation requirements are set forth in the NASA Federal Acquisition Regulation Supplement (NASA/FAR Supplement (NFS)), Subpart 1842.72, NASA Contractor Financial Management Reporting. The standard contract clause for implementing NASA contractor financial management reporting is set forth in NFS 1852.242-73, NASA Contractor Financial Management Reporting.

1.4.2 Deviations from financial management reporting provisions set forth in NFS 1842.72, NASA Contractor Financial Management Reporting, require approval in accordance with NFS 1801.471, Procedure for requesting deviations.

1.4.3 Where a specific contractual requirement differs from the standard system set forth in this NPR, but is determined to be in the best interest of the Government and does not eliminate any data elements required by the standard NF 533 formats, deviations may be approved by the NASA Contracting Officer with the concurrence of the NASA Center Chief Financial Officer and cognizant Project Manager. Such approval shall be documented and retained, with the supporting rationale, in the NASA contract file. Examples of such exceptions include:

a. Addition of a column for Government fiscal year cumulative costs to the standard NF 533 M or NF 533 Q formats.

b. Substitution of reports generated by contractors existing management systems or PMS reports for NF 533 formats.

c. Due dates other than those stipulated in this NPR. Due dates earlier than the standard dates set forth in paragraph 3.3 are encouraged whenever feasible. No due date shall be permitted which is later than the date by which the NASA Center Financial Management Office needs the data in order to enter an accurate monthly cost accrual in the accounting system.

1.4.4 Specific cost and labor hour reporting requirements, including the level of detail, shall be delineated in the contract.

1.4.5 Reporting categories shall be stated in the contract by the Contracting Officer and the Project Manager and held as firm as practicable throughout its life to ensure continuity and consistency of information. Any changes in reporting requirements will be accomplished by negotiated contractual modifications.

1.5 NASA Form 533 Reports

1.5.1 Applicability - NF 533 reports are applicable to all cost type, price redetermination, and fixed-price incentive contracts when the following dollar and period of performance criteria are met:

Table A Reporting Criteria And Format

CRITERIA REPORT FORMAT
Contract Value Period of
Performance
NF 533M NF 533Q
$500,000 to $999,999 1 year or more Required Optional
$1,000,000 and greater Less than 1 year Required Optional
$1,000,000 and greater 1 year or more Required Required

1.5.2 NF 533 Q reporting may be waived by the NASA Contracting Officer, with concurrence by the Center Chief Financial Officer and cognizant Project Manager, for support service or task order contracts, when NF 533 M reports and other data are sufficient to ensure accurate monthly cost accruals, track the contractors' actual cost against plans, and forecast resource requirements.

1.5.3 The criteria in Table A apply to the total contract, not solely to any particular performance period. Where it is probable that a contract will ultimately meet the criteria through the exercise of options, execution of change orders or supplemental agreements, or other circumstances, the reporting requirement shall be implemented by the NASA Contracting Officer and Project Manager based on the estimated final contract value, inclusive of options.

1.5.4 Action shall be promptly taken by the NASA Contracting Officer and Project Manager to include the appropriate reporting requirements in contracts not covered at award that subsequently meet the above criteria as a result of change orders or supplemental agreements.

1.5.5 As applied to letter contracts, reporting requirements shall be identified therein by the NASA Contracting Officer and Project Manager.

1.5.6 Determination of the applicability of the criteria shall be based upon the mutually agreed upon scope of work to be accomplished under the definitized contract. If deemed appropriate by the NASA Contracting Officer or necessary to provide the data discussed in paragraph 1.2, NF 533 reporting requirements may be negotiated into other types of contracts and contracts not meeting the above criteria.

1.6 Reports From Subcontractors

1.6.1 Prime contractors are responsible for obtaining financial management data from subcontractors; data submitted by subcontractors should be structured similar to the prime contractors' NF 533 to enable the prime contractor to properly report to NASA. Prime contractors shall ensure subcontract data are available in sufficient time for inclusion in the prime contractors' NF 533 report for the same reporting period. The prime contract may call for copies of subcontractor reports to be submitted directly to NASA. See paragraph 3.3.2.2 for specific subcontract cost reporting requirements.

1.7 Contractors' Privileged Financial and Business Information

1.7.1 To the maximum extent possible, financial management reports should be unclassified. NASA acquires information in financial management reports primarily for purposes of program and project planning and management, contract administration, and accounting. It recognizes that these reports may contain contractor-privileged information. NASA personnel shall ensure that contractors' financial and business information contained in the reports will not be disclosed outside the Government, except in accordance with procedures set forth in 14 CFR 1206, Availability of Agency Records to Members of the Public, and disclosure of such information to other Government agencies will be made in accordance with 44 U.S.C. 3510(b). Where it is necessary to disclose a contractor's confidential financial information to NASA support services contractors (in areas such as information technology or financial services), NASA personnel should first obtain the informed consent to such disclosure of the contractor providing the information.

1.8 Security Classification

1.8.1 Reporting contractors shall ensure appropriate security markings,

consistent with the assigned security classification, are applied to each classified report in accordance with provisions of NPD 1600.2, NASA Security Policy, and NPR 1600.1, NASA Security Program Procedural Requirements.

1.8.2 Security classification markings shall not be used by reporting contractors on documents containing information solely of a privileged financial and business nature.



| TOC | ChangeLog | Preface | Chapter1 | Chapter2 | Chapter3 | AppendixA | AppendixB | AppendixC | ALL |
 
| NODIS Library | Financial Management(9000s) | Search |

DISTRIBUTION:
NODIS


This document does not bind the public, except as authorized by law or as incorporated into a contract. This document is uncontrolled when printed. Check the NASA Online Directives Information System (NODIS) Library to verify that this is the correct version before use: https://nodis3.gsfc.nasa.gov.