![]() |
NASA Procedural Requirements |
NPR 7120.5F Effective Date: August 03, 2021 Expiration Date: August 03, 2026 |
| TOC | ChangeHistory | Preface | Chapter1 | Chapter2 | Chapter3 | AppendixA | AppendixB | | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | ALL | |
a. The Product Owner for each product is indicated in the column titled "Product Owner/Requirement or Best Practice."
b. Products listed in the I-Tables are either requirements or best practices.
c. “R” in the Product Owner/Requirement or Best Practice column indicates that a product is a requirement. Products that are requirements are included in the Compliance Matrix in Appendix C.
d. “BP” in the Product Owner/Requirement or Best Practice column indicates that the product is considered a best practice. The expectation is that the product will be developed in accordance with the I-Table as part of normal program management activities.
a. “Initial” is applied to products that are continuously developed and updated as the program or project matures.
b. “Final” is applied to products that are expected to exist in this final form (e.g., minutes and final reports).
c. “Summary” is applied to products that synthesize the results of work accomplished.
d. “Plan” is applied to products that capture work to be performed in the following phases.
e. “Update” is applied to products that are expected to evolve as the formulation and implementation processes evolve. Only expected updates are indicated. However, any document may be updated as needed.
a. “Preliminary” is the documentation of information as it stabilizes but before it goes under configuration control. It is the initial development leading to a baseline. Some products will remain in a preliminary state for multiple LCRs. The initial preliminary version is likely to be updated at subsequent LCRs but remains preliminary until baselined.
b. “Baseline” indicates putting the product under configuration control so that changes can be tracked, approved, and communicated to the team and any relevant stakeholders. The expectation on products labeled “baseline” is that they will be at least final drafts going into the designated LCR and baselined coming out of the LCR. Baselining of products that will eventually become part of the Program or Project Plan indicates that the product has the concurrence of stakeholders and is under configuration control. Updates to baselined documents require the same formal approval process as the original baseline.
c. “Approve” is used for a product, such as Concept Documentation, that is not expected to be put under classic configuration control but still requires that changes from the “Approved” version are documented at each subsequent “Update.”
d. “Update” is applied to products that are expected to evolve as the formulation and implementation processes evolve. Only expected updates are indicated. However, any document may be updated as needed. Updates to baselined documents require the same formal approval process as the original baseline.
a. Control plans can either be part of the Program or Project Plan or separate stand-alone documents referenced in the appropriate part of the Program or Project Plan.
b. Considerations for determining if a control plan should be a stand-alone document include a requirement that the control plan be stand-alone in the NPR that requires the control plan; differences between when the control plan is baselined and when the Program or Project Plan is baselined; how frequently the control plan will be updated since updates to the Program or Project Plan require signatures; and how long the control plan is.
c. When the control plan is a stand-alone document, the Program or Project Plan contains a reference to the stand-alone document.
a. Unless a specific form, format, document, or document template is identified by the NPR that requires an I-Table product, the documentation format is flexible (e.g., LCR or KDP presentation charts or as part of a document such as the Program or Project Plan).
Table I-1 Uncoupled and Loosely Coupled Program
Milestone Products and Control Plans Maturity Matrix
Products | Product Owner/Requirement or Best Practice | Formulation | Implementation | |
---|---|---|---|---|
KDP I1 | KDP II - n | |||
SRR | SDR | PIR | ||
1. FAD [Required per NPR 7120.5] | NASA AA/R | Baseline | ||
2. PCA [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | |
3. Program Plan [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | Update |
3.a. Mission Directorate requirements and constraints [Required per NPR 7123.1] | OCE/R | Baseline | Update | |
3.b. Traceability of program-level requirements on projects to the Agency strategic goals and Mission Directorate requirements and constraints [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | |
3.c. Documentation of driving ground rules and assumptions on the program [Required per NPR 7120.5} | NASA AA/R | Preliminary | Baseline | |
4. Interagency and international agreements | NASA AA/R | Preliminary | Baseline | |
5. ASM Decision Memorandum or ASM meeting summary [additional information in NPD 1000.5] | NASA AA/R | Final | ||
6. Risk mitigation plans and resources for significant risks [Required by NPR 7120.5] | NASA AA/R | Initial | Update | Update |
7. Documented Cost and Schedule Baselines [Required per NPR 7120.5] | OCFO-SID/R | Preliminary | Baseline | Update |
8. Documentation of Basis of Estimate (cost and schedule) [Required per NPR 7120.5] | OCFO-SID/R | Preliminary | Baseline | Update |
9. Documentation of performance against plan/baseline, including status/closure of formal actions from previous KDP [Required by NPR 7120.5] | NASA AA/R | Summary | Summary | Summary |
10. Industrial Base and Supply Chain Risk Management (SCRM) Strategy and Status [Required per NPR 8735.2] | OSMA/R | Preliminary | Baseline | Update |
Program Plan Control Plans | ||||
1. Technical, Schedule, and Cost Control Plan [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | |
2. Safety and Mission Assurance Plan [Required per NPRs 8705.2 and 8705.4] | OSMA/R | Preliminary | Baseline | |
3. Risk Management Plan [Required per NPR 8000.4] | OSMA/R | Preliminary | Baseline | |
4. Acquisition Strategy [Required per NPD 1000.5] | NASA AA/R | Preliminary | Baseline | |
5. Technology Development Plan [additional information in NPR 7500.2, NPR 7123.1, and NPR 7120.5] | OCE/BP | Preliminary | Baseline | |
6. Systems Engineering Management Plan [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | |
7. System Security Plan [Required per NPR 2810.1] | OCIO/R | Preliminary | Baseline | Update |
8. Review Plan [Required per NPR 7120.5]2 | NASA AA/R | Baseline | Update | |
9. NEPA Compliance Plan [Required per NPR 8580.1] | OSI-EMD/R | Baseline | ||
10. Configuration Management Plan [Required per NPR 7120.5; additional information in NPR 7123.1 and SAE/EIA 649] | OCE/R | Baseline | ||
11. Security Plan [Required per NPR 1040.1 and NPR 1600.1] | OPS/R | Baseline | ||
12. Technology Transfer (formerly Export) Control Plan [Required per NPR 2190.1] | OIIR/R | Baseline | ||
13. Communications Plan [additional information in NPR 7120.5] | OComm/BP | Preliminary | Baseline | |
14. Knowledge Management Plan [additional information in NPD 7120.4 and NPD 7120.6] | OCE/BP | Preliminary | Baseline | |
15. Quality Assurance Surveillance Plan [Required per NPR 8735.2 and NASA FAR Supplement part 1837.604] | OSMA/R | Preliminary | Baseline | Update |
1 If desired, the Decision Authority may request a KDP 0 be performed generally following SRR.
2 Review Plan should be baselined before the first review. |
Table I-2 Tightly Coupled Program Milestone Products Maturity Matrix
Products | Product Owner/Requirement or Best Practice | Formulation | Implementation | ||||||
---|---|---|---|---|---|---|---|---|---|
KDP 0 | KDP I | KDP II | KDP III | KDP n | |||||
SRR | SDR | PDR | CDR | SIR | ORR | MRR/FRR | DR | ||
1. FAD [Required per NPR 7120.5] | NASA AA/R | Baseline | |||||||
2. PCA [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | ||||||
3. Program Plan [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | Update | Update | Update | Update | Update | Update |
3.a. Mission Directorate requirements and constraints [Required per NPR 7123.1] | OCE/R | Baseline | Update | Update | |||||
3.b. Traceability of program-level requirements on projects to the Agency strategic goals and Mission Directorate requirements and constraints [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | |||||
3.c. Documentation of driving ground rules and assumptions on the program [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | Update | Update | Update | |||
4. Interagency and international agreements | NASA AA/R | Preliminary | Baseline | Update | |||||
5. ASM Decision Memorandum or ASM meeting summary [additional information in NPD 1000.5] | NASA AA/R | Final | |||||||
6. Risk mitigation plans and resources for significant risks [Required by NPR 7120.5] | NASA AA/R | Initial | Update | Update | Update | Update | Update | Update | Update |
7. Documented Cost and Schedule Baselines [Required per NPR 7120.5] | OCFO-SID/R | Preliminary | Preliminary | Baseline | Update | Update | Update | Update | Update |
8. Documentation of Basis of Estimate (cost and schedule) [Required per NPR 7120.5] | OCFO-SID/R | Preliminary | Preliminary | Baseline | Update | Update | Update | Update | Update |
9. CADRe [Required by NPR 7120.5] | OCFO-SID/R | Baseline | Update | Update | Update | Update | Update1 | Update | |
10. Shared Infrastructure2, Staffing, and Scarce Material Requirements and Plans | NASA AA/R | Initial | Update | Update | Update | ||||
11. Documentation of performance against plan/baseline, including status/closure of formal actions from previous KDP [Required by NPR 7120.5] | NASA AA/R | Summary | Summary | Summary | Summary | Summary | Summary | Summary | |
12. Industrial Base and Supply Chain Risk Management (SCRM) Strategy and Status [Required per NPR 8735.2] | OSMA/R | Preliminary | Baseline | Update | Update | ||||
1 The CADRe for MRR/FRR is considered the “Launch CADRe” to be completed after the launch. 2 Shared infrastructure includes facilities that are required by more than one of the program’s projects. |
Table I-3 Tightly Coupled Program Plan Control Plans Maturity Matrix
(See Appendix G Template for Control Plan Details.) | Product Owner/Requirement or Best Practice | Formulation | Implementation | ||||||
---|---|---|---|---|---|---|---|---|---|
KDP 0 | KDP I | KDP II | KDP III | KDP n | |||||
SRR | SDR | PDR | CDR | SIR | ORR | MRR/FRR | DR | ||
1. Technical, Schedule, and Cost Control Plan [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | Update | |||||
2. Safety and Mission Assurance Plan [Required per NPRs 8705.2 and 8705.4] | OSMA/R | Preliminary | Baseline | Update | Update | Update (SMSR) | |||
3. Risk Management Plan [Required per NPR 8000.4] | OSMA/R | Preliminary | Baseline | Update | |||||
4. Acquisition Strategy [Required per NPD 1000.5] | NASA AA/R | Preliminary Strategy | Baseline | Update | |||||
5. Technology Development Plan [additional information in NPR 7500.2, NPR 7123.1, and NPR 7120.5] | OCE/BP | Preliminary | Baseline | Update | |||||
6. Systems Engineering Management Plan [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | ||||||
7. Verification and Validation Plan [Required per NPR 7120.5, additional information in NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | Update | ||||
8. System Security Plan [Required per NPR 2810.1] | OCIO/R | Preliminary | Update | Baseline | Update | Update | |||
9. Review Plan [Required per NPR 7120.5]1 | NASA AA/R | Baseline | Update | Update | |||||
10. Mission Operations Plan [Required per NPR 7120.5] | OCE/R | Preliminary | Baseline | Update | |||||
11. NEPA Compliance Plan [Required per NPR 8580.1] | OSI-EMD/R | Preliminary | Baseline | Update | |||||
12. Integrated Logistics Support Plan [Required per NPD 7500.1] | OSI-LMD/R | Preliminary | Baseline | Update | |||||
13. Science Data Management Plan [additional information in NPD 2200.1 and NPRs 2200.2, 1441.1, and 8715.24] | SMD/BP | Preliminary Science Data Requirements | Preliminary | Baseline | Update | ||||
14. Configuration Management Plan [Required per NPR 7120.5; additional information in NPR 7123.1 and SAE/EIA 649] | OCE/R | Preliminary | Baseline | Update | |||||
15. Security Plan [Required per NPR 1040.1 and NPR 1600.1] | OPS/R | Preliminary | Baseline | Update Annually | |||||
16. Technology Transfer (formerly Export) Control Plan [Required per NPR 2190.1] | OIIR/R | Preliminary | Baseline | Update | |||||
17. Communications Plan [additional information in NPR 7120.5] | OComm/BP | Preliminary | Baseline | Update | Update | ||||
18. Knowledge Management Plan [additional information in NPD 7120.4 and NPD 7120.6] | OCE/BP | Preliminary | Baseline | Update | Update | ||||
19. Human-Rating Certification Package [Required per NPR 8705.2] | OSMA/R | Initial | Update | Update | Update | Update | Approve Certification | ||
20. Quality Assurance Surveillance Plan [Required per NPR 8735.2 and NASA FAR Supplement part 1837.604] | OSMA/R | Preliminary | Baseline | Update | Update | Update | |||
21. Orbital Collision Avoidance Plan [Required per NID 7120.132] | OCE/R | Baseline | Update | ||||||
22. Human Systems Integration Approach [additional information in NASA/SP-20210010952 NASA HSI Handbook and NPR 7123.1] | OCE-OSMA-OCHMO/R | Baseline | Update | Update | Update | ||||
1 Review Plan should be baselined before the first review. |
Table I-4 Project Milestone Products Maturity Matrix
Products | Product Owner/ Requirement or Best Practice | Pre-Phase A KDP A | Phase A KDP B | Phase B KDP C | Phase C KDP D | Phase D KDP E | Phase E KDP F | Phase F | |||
---|---|---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/FRR | DR | DRR | ||
Headquarters and Program Products1 | |||||||||||
1. FAD [Required per NPR 7120.5] | NASA AA/R | Baseline | |||||||||
2. Program Plan [Required per NPR 7120.5] | NASA AA/R | Baseline | |||||||||
2.a. Applicable Agency strategic goals [Required per NPR 7123.1] | NASA AA/R | Baseline | Update | Update | |||||||
2.b. Documentation of program-level requirements and constraints on the project (from the Program Plan) and stakeholder expectations, including mission objectives/goals and mission success criteria [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | Update | ||||||
2.c. Documentation of driving mission, technical, and programmatic ground rules and assumptions [Required per NPR 7120.5] | NASA AA/R | Preliminary | Preliminary | Baseline | Update | Update | Update | ||||
3. Partnerships and interagency and international agreements | NASA AA/R | Preliminary | Update | Baseline U.S. partnerships and agreements | Baseline international agreements | ||||||
4. ASM Decision Memorandum or ASM meeting summary [additional information in NPD 1000.5] | NASA AA/R | Final | |||||||||
5. Mishap Preparedness and Contingency Plan [Required per NPR 8621.1] | OSMA/R | Preliminary | Update | Baseline (SMSR) | Update | Update | |||||
Project Technical Products2 | |||||||||||
1. Concept Documentation [Required per NPR 7123.1] | OCE/R | Approve | Update | Update | Update | ||||||
2. Mission, Spacecraft, Ground, and Payload Architectures [Required per NPR 7123.1] | OCE/R | Preliminary mission and spacecraft architecture(s) with key drivers | Baseline mission and spacecraft architecture, preliminary ground and payload architectures. Classify payload(s) by risk per NPR 8705.4. | Update mission and spacecraft architecture, baseline ground and payload architectures | Update mission, spacecraft, ground and payload architectures | ||||||
3. Project-Level, System, and Subsystem Requirements [Required per NPR 7123.1] | OCE/R | Preliminary project-level requirements | Baseline project-level and system-level requirements | Update Project-level and system-level requirements, Preliminary subsystem requirements | Update project-level and system-level requirements. Baseline subsystem requirements | ||||||
4. Design Documentation [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | Update | ||||||
5. Operations Concept Documentation [Required per NPR 7120.5] | OCE/R | Preliminary | Preliminary | Preliminary | Baseline | ||||||
6. Technology Readiness Assessment Documentation [Required per NPR 7120.5 Appendix F FA Template] | OCE/R | Initial | Update | Update | Update | Update | |||||
7. Engineering Development Assessment Documentation [Required per NPR 7120.5 Appendix F FA Template] | OCE/R | Initial | Update | Update | Update | ||||||
8. Heritage Assessment Documentation [Required per NPR 7120.5 Appendix F FA Template] | OCE/R | Initial | Update | Update | Update | ||||||
9. Systems Safety Analyses (e.g., safety data packages) [Baseline at CDR] [Required per NPR 8715.3] | OSMA/R | Preliminary | Baseline | Update | Update | Update | |||||
10. Payload Safety Process Deliverables [Required per NPR 8715.7] | OSMA/R | Preliminary | Preliminary | Baseline | |||||||
11. Verification and Validation Report [Required per NPR 7123.1] | OCE/R | Prelim-inary | Baseline | ||||||||
12. Operations Handbook [additional information in NPR 7120.5 Appendix A] | OCE/R | Preliminary | Baseline | Update | Update | ||||||
13. Orbital Debris Assessment [Required per NPR 8715.6; additional information in NASA-STD-8719.14] | OSMA/R | Initial Assessment | Preliminary design ODAR | Detailed design ODAR | Final ODAR (SMSR) | ||||||
14. End of Mission Plans [Required per NPR 8715.6; additional information in NASA-STD-8719.14, App B] | OSMA/R | Baseline (SMSR) | Update per 8715.6 | Update | |||||||
15. Final Mission Report [additional information in NPR 7120.5 Appendix A] | OCE/BP | Final | |||||||||
16. Decommissioning/Disposal Plan [Required per NPR 7123.1] | OCE/R | Baseline | Update | Update Dispos-al portions | |||||||
17. Industrial Base and Supply Chain Risk Management (SCRM) Strategy and Status [Required per NPR 8735.2] | OSMA/R | Preliminary | Update | Update | Baseline | Update | |||||
18. Criticality Identification Method for Hardware [Required per NPR 8735.2] | OSMA/R | Preliminary | Update | Update | Baseline | Update | |||||
19. Hardware Quality Data Management Analytics [additional information in NPR 8735.2] | OSMA/BP | Preliminary | Update | Update | Baseline | Update | Update | Update | Update | ||
Project Management, Planning, and Control Products | |||||||||||
1. Formulation Agreement [Required per NPR 7120.5] | NASA AA/R | Baseline for Phase A; Preliminary for Phase B | Baseline for Phase B | ||||||||
2. Project Plan [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | ||||||||
3. Documentation of performance against Formulation Agreement (see #1 above) or against plans for work to be accomplished during Implementation life-cycle phase, including performance against baselines and status/closure of formal actions from previous KDP [Required by NPR 7120.5] | NASA AA/R | Summary | Summary | Summary | Summary | Summary | Summary | Summary | Summary | ||
4.Project Baselines | |||||||||||
4.a. Top technical, cost, schedule and safety risks, risk mitigation plans, and associated resources [Required by NPR 7120.5] | NASA AA/R | Initial | Update | Update | Update | Update | Update | Update | Update | Update | Update |
4.b. Staffing requirements and plans [Required by NPR 7120.5] | NASA AA/R | Initial | Update | Update | Update | Update | Update | ||||
4.c.i Infrastructure requirements and plans [Required per NPR 9250.1, NPD 8800.14 and NPR 8820.2] Business case analysis for infrastructure [Required per NPR 8800.15.] | OSI-FRED/R | Initial | Update | Update | Update | Update | |||||
4.c.ii Capitalization Determination Form (CDF) (NASA Form 1739) [Required per NPR 9250.1] | OCFO/R | Initial | Update | Update | Update | Update | |||||
4.d. Schedule [Required per NPR 7120.5] | OCFO-SID/R | Risk informed at project level with preliminary Phase D completion ranges |
Risk informed at system level with preliminary Phase D completion ranges | Risk informed at subsystem level with preliminary Phase D completion ranges or high and low schedule values with JCL3. Preliminary Integrated Master Schedule | Risk informed and cost- loaded. Baseline Integrated Master Schedule | Update IMS | Update IMS | Update IMS | Update IMS | Update IMS | Update IMS |
4.e. Cost Estimate [Required per NPR 7120.5] | OCFO-SID/R | Preliminary Range estimate | Update | Risk-informed range estimate or high and low-cost values with JCL3 | Risk-informed Baseline | Update | Update | Update | Update | Update | Update |
4.f. Basis of Estimate (cost and schedule) [Required per NPR 7120.5] | OCFO-SID/R | Initial (for range) | Update (for range) | Update (for range or high and low values with JCL3) | Update for cost and schedule estimate | Update | Update | Update | Update | Update | Update |
4.g. Confidence Level(s) and supporting documentation [Required per NPR 7120.5] | OCFO-SID/R | Preliminary cost confidence level and preliminary schedule confidence level or JCL3 | Baseline Joint Cost and Schedule Confidence Level | Update4 | Update5 | ||||||
4.h. External Cost and Schedule Commitments [Required per NPR 7120.5] | OCFO-SID/R | Preliminary for ranges or high and low values with JCL3 | Baseline | ||||||||
4.i. CADRe [Required per NPR 7120.5] | OCFO-SID/R | Baseline | Update | Update | Update | Update | Update6 | Update | |||
4.j PMB [Required per NPR 7120.5 and NASA EVM Capability Process Documentation] | OCFO-SID/R | Baseline | Update | Update | Update | Update | |||||
1 These products are developed by the Mission Directorate. 2 These document the work of the key technical activities performed in the associated phases. 3 Projects with LCC or initial capability cost of $1B or over develop high and low values for cost and schedule with the corresponding JCL values at KDP B per Section 2.4.3.1.a. 4 Projects with LCC or initial capability cost of $1B or over update the JCL at CDR per Section 2.4.3.3. 5 Projects with LCC or initial capability cost of $1B or over update the JCL at KDP D per Section 2.4.3.4 if current development costs exceed development ABC cost by 5 percent or more. 6 The CADRe for MRR/FRR is considered the “Launch CADRe” to be completed after the launch. |
Table I-5 Project Plan Control Plans Maturity Matrix
(See Appendix H Template for Control Plan Details.) | Product Owner/Requirement or Best Practice | Pre-Phase A | Phase A KDP B | Phase B KDP C | Phase C KDP D | Phase D KDP E | Phase E KDP F | |||
---|---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/ FRR | DR | ||
1. Technical, Schedule, and Cost Control Plan [Required per NPR 7120.5] | NASA AA/R | Approach for managing schedule and cost during Phase A1 | Preliminary | Baseline | Update | |||||
2. Safety and Mission Assurance Plan [Required per NPRs 8705.2 and 8705.4] | OSMA/R | Baseline | Update | Update | Update | Update (SMSR) | Update | |||
3. Risk Management Plan [Required per NPR 8000.4] | OSMA/R | Approach for managing risks during Phase A1 | Baseline | Update | Update | |||||
4. Acquisition Strategy [Required per NPD 1000.5] | NASA AA/R | Preliminary Strategy | Baseline | Update | Update | |||||
5. Technology Development Plan (may be part of Formulation Agreement) [additional information in NPR 7500.2, NPR 7123.1, and NPR 7120.5] | OCE/BP | Baseline | Update | Update | Update | |||||
6. Systems Engineering Management Plan [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | Update | |||||
7. System Security Plan [Required per NPR 2810.1] | OCIO/R | Preliminary | Update | Baseline | Update | Update | ||||
8. Software Management Plan(s) [Required per NPR 7150.2; additional information in NASA-STD-8739.8] | OCE/R | Preliminary | Baseline | Update | ||||||
9. Verification and Validation Plan [Required per NPR 7120.5, additional information in NPR 7123.1] | OCE/R | Preliminary Approach2 | Preliminary | Baseline | Update | Update | ||||
10. Review Plan [Required per NPR 7120.5]3 | NASA AA/R | Preliminary | Baseline | Update | Update | |||||
11. Mission Operations Plan [Required per NPR 7120.5] | OCE/R | Preliminary | Baseline | Update | ||||||
12. NEPA Compliance Plan [Required per NPR 8580.1] | OSI-EMD/R | Baseline | ||||||||
13. Integrated Logistics Support Plan [Required per NPD 7500.1] | OSI-LMD/R | Approach for managing logistics2 | Preliminary | Preliminary | Baseline | Update | ||||
14. Science Data Management Plan [additional information in NPD 2200.1 and NPRs 2200.2, 1441.1, and 8715.24] | SMD/BP | Preliminary Science Data Requirements | Preliminary | Baseline | Update | |||||
15. Integration Plan [Required per NPR 7120.5] | OCE/R | Preliminary approach2 | Preliminary | Baseline | Update | |||||
16. Configuration Management Plan [Required per NPR 7120.5; additional information in NPR 7123.1 and SAE/EIA 649] | OCE/R | Baseline | Update | Update | ||||||
17. Security Plan [Required per NPR 1040.1 and NPR 1600.1] | OPS/R | Preliminary | Baseline | Update annually | ||||||
18. Project Protection Plan [Required per NPR 1058.1, additional information in NASA-STD-1006] | OCE/R | Preliminary | Baseline | Update | Update | Update | Update | Update annually | ||
19. Technology Transfer (formerly Export) Control Plan [Required per NPR 2190.1] | OIIR/R | Preliminary | Baseline | Update | ||||||
20. Knowledge Management Plan [additional information in NPD 7120.4 and NPD 7120.6] | OCE/BP | Approach for managing during Phase A1 | Preliminary | Baseline | Update | |||||
21. Human-Rating Certification Package [Required per NPR 8705.2] | OSMA/R | Preliminary approach2 | Initial | Update | Update | Update | Update | Approve Certification | ||
22. Planetary Protection Plan [Required per NPD 8020.7 and NPR 8715.24] | OSMA/R | Planetary Protection Categorization (if applicable) | Baseline | |||||||
23. Nuclear Launch Authorization Plan [additional information in NPR 8715.26] | OSMA/R | Baseline (mission has nuclear materials) | ||||||||
24. Range Safety Risk Management Process Documentation [Required per NPR 8715.5] | OSMA/R | Preliminary | Preliminary | Baseline | ||||||
25. Communications Plan [additional information in NPR 7120.5] | OComm/BP | Preliminary | Baseline | Update | Update | |||||
26. Quality Assurance Surveillance Plan [Required per NPR 8735.2 and NASA FAR Supplement part 1837.604] | OSMA/R | Preliminary | Baseline | Update | Update | Update | ||||
27. Orbital Collision Avoidance Plan [Required per NID 7120.132] | OCE/R | Baseline | Update | |||||||
28. Human Systems Integration Approach [additional information in NASA/SP-20210010952 NASA HSI Handbook and NPR 7123.1] | OCE-OSMA-OCHMO/R | Preliminary | Baseline | Update | Update | Update | ||||
1 Not the Plan, but documentation of high-level process. May be documented in MCR briefing package. 2 Not the Plan, but documentation of considerations that might impact the cost and schedule baselines. May be documented in MCR briefing package. 3 Review Plan should be baselined before the first review. |
Table I-6 Single-Project Program Milestone Products Maturity Matrix
Products | Product Owner/Requirement or Best Practice | Pre-Phase A KDP A | Phase A KDP B | Phase B KDP C | Phase C KDP D | Phase D KDP E | Phase E KDP F | Phase F | |||
---|---|---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/FRR | DR | DRR | ||
Headquarters Products1 | |||||||||||
1. FAD [Required per NPR 7120.5] | NASA AA/R | Baseline | |||||||||
2. PCA [Required per NPR 7120.5] | NASA AA/R | Preliminary | Baseline | ||||||||
3. Traceability of Agency strategic goals and Mission Directorate requirements and constraints to program/project-level requirements and constraints. [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | Update | ||||||
4. Documentation of driving mission, technical, and programmatic ground rules and assumptions [Required per NPR 7120.5] | NASA AA/R | Preliminary | Preliminary | Baseline | Update | Update | Update | ||||
5. Partnerships and inter-agency and international agreements | NASA AA/R | Preliminary | Update | Baseline U.S. partnerships and agreements | Baseline international agreements | ||||||
6. ASM Decision Memorandum or ASM meeting summary [additional information in NPD 1000.5] | NASA AA/R | Final | |||||||||
7. Mishap Preparedness and Contingency Plan [Required per NPR 8621.1] | OSMA/R | Preliminary | Update | Baseline (SMSR) | Update | Update | |||||
Single-Project Program Technical Products2 | |||||||||||
1. Concept Documentation [Required per NPR 7123.1] | OCE/R | Approve | Update | Update | Update | ||||||
2. Mission, Spacecraft, Ground, and Payload Architectures [Required per NPR 7123.1] | OCE/R | Preliminary mission and spacecraft architecture(s) with key drivers | Baseline mission and spacecraft architecture, preliminary ground and payload architectures. Classify payload(s) by risk per NPR 8705.4. | Update mission and spacecraft architecture, baseline ground and payload architectures | Update mission, spacecraft, ground, and payload architectures | ||||||
3. Project-Level, System, and Subsystem Requirements [Required per NPR 7123.1] | OCE/R | Preliminary project-level requirements | Baseline project-level and system-level requirements | Update Project-level and system-level requirements, Preliminary subsystem requirements | Update project-level and system-level requirements. Baseline subsystem requirements | ||||||
4. Design Documentation [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | Update | ||||||
5. Operations Concept Documentation [Required per NPR 7120.5] | OCE/R | Preliminary | Preliminary | Preliminary | Baseline | ||||||
6. Technology Readiness Assessment Documentation [Required per NPR 7120.5 Appendix F FA Template] | OCE/R | Initial | Update | Update | Update | Update | |||||
7. Engineering Development Assessment Documentation [Required per NPR 7120.5 Appendix F FA Template] | OCE/R | Initial | Update | Update | Update | ||||||
8. Heritage Assessment Documentation [Required per NPR 7120.5 Appendix F FA Template] | OCE/R | Initial | Update | Update | Update | ||||||
9. Systems Safety Analyses (e.g., safety data packages) [Baseline at CDR] [Required per NPR 8715.3] | OSMA/R | Preliminary | Baseline | Update | Update | Update | |||||
10. Payload Safety Process Deliverables [Required per NPR 8715.7] | OSMA/R | Preliminary | Preliminary | Baseline | |||||||
11. Verification and Validation Report [Required per NPR 7123.1] | OCE/R | Prelim-inary | Baseline | ||||||||
12. Operations Handbook [additional information in NPR 7120.5 Appendix A] | OCE/R | Preliminary | Baseline | Update | Update | ||||||
13. Orbital Debris Assessment [Required per NPR 8715.6; additional information in NASA-STD-8719.14] | OSMA/R | Initial Assessment | Preliminary design ODAR | Detailed design ODAR | Final ODAR (SMSR) | ||||||
14. End of Mission Plans [Required per NPR 8715.6; additional information in NASA-STD-8719.14, App B] | OSMA/R | Baseline (SMSR) | Update per 8715.6 | Update | |||||||
15. Final Mission Report [additional information in NPR 7120.5 Appendix A] | OCE/BP | Final | |||||||||
16. Decommissioning/Disposal Plan [Required per NPR 7123.1] | OCE/R | Baseline | Update | Update disposal portions | |||||||
17. Industrial Base and Supply Chain Risk Management (SCRM) Strategy and Status [Required per NPR 8735.2] | OSMA/R | Preliminary | Update | Update | Baseline | Update | |||||
18. Criticality Identification Method for Hardware [Required per NPR 8735.2] | OSMA/R | Preliminary | Update | Update | Baseline | Update | |||||
19. Hardware Quality Data Management Analytics [additional information in NPR 8735.2] | OSMA/BP | Preliminary | Update | Update | Baseline | Update | Update | Update | Update | ||
Single-Project Program Management, Planning, and Control Products | |||||||||||
1. Formulation Agreement [Required per NPR 7120.5] | NASA AA/R | Baseline for Phase A; Preliminary for Phase B | Baseline for Phase B | ||||||||
2. Program Plan [Required per NPR 7120.5]3 | NASA AA/R | Preliminary | Baseline | ||||||||
3. Project Plan [Required per NPR 7120.5]3 | NASA AA/R | Preliminary | Baseline | ||||||||
4. Documentation of performance against Formulation Agreement (see #1 above) or against plans for work to be accomplished during Implementation life-cycle phase, including performance against baselines and status/closure of formal actions from previous KDP [Required per NPR 7120.5] | NASA AA/R | Summary | Summary | Summary | Summary | Summary | Summary | Summary | Summary | ||
5.Project Baselines | |||||||||||
5.a. Top technical, cost, schedule and safety risks, risk mitigation plans, and associated resources [Required per NPR 7120.5] | NASA AA/R | Initial | Update | Update | Update | Update | Update | Update | Update | Update | Update |
5.b. Staffing requirements and plans [Required by NPR 7120.5] | NASA AA/R | Initial | Update | Update | Update | Update | Update | ||||
5.c.i. Infrastructure requirements and plans [Required per NPR 9250.1, NPD 8800.14, and NPR 8820.2] Business case analysis for infrastructure [Required per NPR 8800.15.] | OSI-FRED/R | Initial | Update | Update | Update | Update | |||||
5.c.ii Capitalization Determination Form (CDF) (NASA Form 1739) [Required per NPR 9250.1] | OCFO/R | Initial | Update | Update | Update | Update | |||||
5.d. Schedule [Required per NPR 7120.5] | OCFO-SID/R | Risk informed at project level with preliminary Phase D completion ranges | Risk informed at system level with preliminary Phase D completion ranges | Risk informed at subsystem level with preliminary Phase D completion ranges or high and low schedule values with JCL.4 Prelim-inary IMS | Risk informed and cost- loaded. Baseline Integrated Master Schedule | Update IMS | Update IMS | Update IMS | Update IMS | Update IMS | Update IMS |
5.e. Cost Estimate [Required per NPR 7120.5] | OCFO-SID/R | Preliminary Range estimate | Update | Risk-informed range estimate or high and low-cost values with JCL4 | Risk-informed baseline | Update | Update | Update | Update | Update | Update |
5.f. Basis of Estimate (cost and schedule) [Required per NPR 7120.5] | OCFO-SID/R | Initial (for range) | Update (for range) | Update (for range or high and low values with JCL4) | Update for cost and schedule estimate | Update | Update | Update | Update | Update | Update |
5.g. Confidence Level(s) and supporting documentation [Required per NPR 7120.5] | OCFO-SID/R | Preliminary cost confidence level and preliminary schedule confidence level or JCL4 | Baseline Joint Cost and Schedule Confidence Level | Update5 | Update6 | ||||||
5.h. External Cost and Schedule Commitments [Required per NPR 7120.5] | OCFO-SID/R | Preliminary for ranges or JCL4 | Baseline | ||||||||
5.i. CADRe [Required per NPR 7120.5] | OCFO-SID/R | Baseline | Update | Update | Update | Update | Update7 | Update | |||
5.j. PMB [Required per NPR 7120.5 and NASA EVM Capability Process Documentation] | OCFO-SID/R | Baseline | Update | Update | Update | Update | |||||
1 These products are developed by the Mission Directorate. 2 These document the work of the key technical activities performed in the associated phases. 3 The Program Plan and Project Plans may be combined with the approval of the MDAA. 4 Single-project programs with LCC or initial capability cost of $1B or over develop high and low values for cost and schedule with corresponding JCL values at KDP B per Section 2.4.3.1.a. 5 Single-project programs with LCC or initial capability cost of $1B or over update the JCL at CDR per Section 2.4.3.3. 6 Projects with LCC or initial capability cost of $1B or over update the JCL at KDP D per Section 2.4.3.4 if current development costs exceed development ABC cost by 5 percent or more. 7 The CADRe for MRR/FRR is considered the “Launch CADRe” to be completed after the launch. |
Table I-7 Single-Project Program Plan Control Plans Maturity Matrix
(See Templates in Appendices G and H for Control Plan Details) | Product Owner/Requirement or Best Practice | Pre-Phase A | Phase A KDP B | Phase B KDP C | Phase C KDP D | Phase D KDP E | Phase E KDP F |
||||
---|---|---|---|---|---|---|---|---|---|---|---|
MCR | SRR | SDR/MDR | PDR | CDR | SIR | ORR | MRR/ FRR | DR | |||
1. Technical, Schedule, and Cost Control Plan [Required per NPR 7120.5] | NASA AA/R | Approach for managing schedule and cost during Phase A1 | Preliminary | Baseline | Update | ||||||
2. Safety and Mission Assurance Plan [Required per NPRs 8705.2 and 8705.4] | OSMA/R | Baseline | Update | Update | Update | Update (SMSR) | Update | ||||
3. Risk Management Plan [Required per NPR 8000.4] | OSMA/R | Approach for managing risks during Phase A1 | Baseline | Update | Update | ||||||
4. Acquisition Strategy [Required per NPD 1000.5] | NASA AA/R | Preliminary Strategy | Baseline | Update | Update | ||||||
5. Technology Development Plan (may be part of Formulation Agreement) [additional information in NPR 7500.2, NPR 7123.1, and NPR 7120.5] | OCE/BP | Baseline | Update | Update | Update | ||||||
6. Systems Engineering Management Plan [Required per NPR 7123.1] | OCE/R | Preliminary | Baseline | Update | Update | ||||||
7. System Security Plan [Required per NPR 2810.1] | OCIO/R | Preliminary | Update | Baseline | Update | Update | |||||
8. Software Management Plan(s) [Required per NPR 7150.2; additional information in NASA-STD-8739.8] | OCE/R | Preliminary | Baseline | Update | |||||||
9. Verification and Validation Plan [Required per NPR 7120.5, additional information in NPR 7123.1] | OCE/R | Preliminary Approach2 | Preliminary | Baseline | Update | Update | |||||
10. Review Plan [Required per NPR 7120.5]3 | NASA AA/R | Preliminary | Baseline | Update | Update | ||||||
11. Mission Operations Plan [Required per NPR 7120.5] | OCE/R | Preliminary | Baseline | Update | |||||||
12. NEPA Compliance Plan [Required per NPR 8580.1] | OSI-EMD/R | Baseline | |||||||||
13. Integrated Logistics Support Plan [Required per NPD 7500.1] | OSI-LMD/R | Approach for managing logistics2 | Preliminary | Preliminary | Baseline | Update | |||||
14. Science Data Management Plan [additional information in NPD 2200.1 and NPRs 2200.2, 1441.1, and 8715.24] | SMD/BP | Preliminary Science Data Requirements | Preliminary | Baseline | Update | ||||||
15. Integration Plan [Required per NPR 7120.5] | OCE/R | Preliminary approach2 | Preliminary | Baseline | Update | ||||||
16. Configuration Management Plan [Required per NPR 7120.5; additional information in NPR 7123.1 and SAE/EIA 649] | OCE/R | Baseline | Update | Update | |||||||
17. Security Plan [Required per NPR 1040.1 and NPR 1600.1] | OPS/R | Preliminary | Baseline | Update annually | |||||||
18. Project Protection Plan [Required per NPR 1058.1, additional information in NASA-STD-1006] | OCE/R | Preliminary | Baseline | Update | Update | Update | Update | Update annually | |||
19. Technology Transfer (formerly Export) Control Plan [Required per NPR 2190.1] | OIIR/R | Preliminary | Baseline | Update | |||||||
20. Knowledge Management Plan [additional information in NPD 7120.4 and NPD 7120.6] | OCE/BP | Approach for managing during Phase A1 | Preliminary | Baseline | Update | ||||||
21. Human-Rating Certification Package [Required per NPR 8705.2] | OSMA/R | Preliminary approach2 | Initial | Update | Update | Update | Update | Approve Certification | |||
22. Planetary Protection Plan [Required per NPD 8020.7 and NPR 8715.24] | OSMA/R | Planetary Protection Categorization (if applicable) | Baseline | ||||||||
23. Nuclear Launch Authorization Plan [additional information in NPR 8715.26] | OSMA/R | Baseline (mission has nuclear materials) | |||||||||
24. Range Safety Risk Management Process Documentation [Required per NPR 8715.5] | OSMA/R | Preliminary | Preliminary | Baseline | |||||||
25. Communications Plan [additional information in NPR 7120.5] | OComm/BP | Preliminary | Baseline | Update | Update | ||||||
26. Quality Assurance Surveillance Plan [Required per NPR 8735.2 and NASA FAR Supplement part 1837.604] | OSMA/R | Preliminary | Baseline | Update | Update | Update | |||||
27. Orbital Collision Avoidance Plan [Required per NID 7120.132] | OCE/R | Baseline | Update | ||||||||
28. Human Systems Integration Approach [additional information in NASA/SP-20210010952 NASA HSI Handbook and NPR 7123.1] | OCE-OSMA-OCHMO/R | Preliminary | Baseline | Update | Update | Update | |||||
1 Not the Plan, but documentation of high-level process. May be documented in MCR briefing package. 2 Not the Plan, but documentation of considerations that might impact the cost and schedule baselines. May be documented in MCR briefing package. 3 Review Plan should be baselined before the first review. |
| TOC | ChangeHistory | Preface | Chapter1 | Chapter2 | Chapter3 | AppendixA | AppendixB | | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | ALL | |
| NODIS Library | Program Formulation(7000s) | Search | |
This document does not bind the public, except as authorized by law or as incorporated into a contract. This document is uncontrolled when printed. Check the NASA Online Directives Information System (NODIS) Library to verify that this is the correct version before use: https://nodis3.gsfc.nasa.gov.