NASA Procedures and Guidelines |
|||||
This Document is Obsolete and Is No Longer Used.
|
|||||
|
|||||
|
|
||||
| TOC | Change History | Preface | Prologue | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | ALL | |
This appendix describes the recommended best practices for technical reviews.
a. The MCR will affirm the mission need and examine the proposed mission's objectives and the concept for meeting those objectives. It is an internal review that usually occurs at the cognizant organization for system development.
b. The MCR should be completed prior to entering the concept development phase.
c. Entrance Criteria. The MCR should include, for hardware and software system elements, availability of the products in Table G-1 to the cognizant participants prior to the review.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-1 was accomplished to complete the objectives of the MCR.
Mission Concept Review | |
Entrance Criteria |
Success Criteria |
|
|
a. The SRR and/or MDR examines the functional and performance requirements defined for the system and the preliminary program or project plan and ensures that the requirements and the selected concept will satisfy the mission.
b. SRR and/or MDR is typically conducted during the concept development phase following completion of the concept studies phase, following baselining of the Systems Engineering Management Plan (SEMP) and before the preliminary design phase, the Agency Pre-Non-Advocate Review (PNAR), and System Definition Review (SDR).
c. Entrance Criteria. Prior to the execution of the SRR and/orMDR the activities and products identified in Table G-2 should be completed and documentation provided to all participants prior to the review. Also, precursor reviews should be completed.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-2 was accomplished to complete the objectives of the SRR and/or MDR.
System Requirements Review and/or Mission Definition Review |
|
Entrance Criteria |
Success Criteria |
|
|
a. The SDR examines the proposed system architecture/design and the flow down to all functional elements of the system.
b. SDR is conducted early in the preliminary design phase, after the Pre-Non-Advocate Review (PNAR) and before the Preliminary Design Review (PDR).
c. Entrance Criteria. Prior to the execution of the SDR, the activities and products identified in Table G-3 should be completed and documentation provided to all participants prior to the review. Also, precursor reviews should be completed.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-3 was accomplished to complete the objectives of the SDR.
System Definition Review | |
Entrance Criteria |
Success Criteria |
|
|
b. PDR occurs near the completion of the preliminary design phase as the last review in the Formulation Phase and before the Agency Non-Advocate Review (NAR).
c. Entrance Criteria. Prior to the execution of the PDR the activities and products identified in Table G-4 should be completed and documentation provided to all participants prior to the review. Also, precursor reviews should be completed.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-4 was accomplished to complete the objectives of the PDR.
Preliminary Design Review | |
Entrance Criteria |
Success Criteria |
|
|
Critical Design Review | |
Entrance Criteria |
Success Criteria |
|
|
b. A TRR is held prior to commencement of verification testing.
c. Entrance Criteria. Prior to the execution of a TRR, the activities and products identified in Table G-6 should be completed and documentation provided to all participants prior to the review.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-6 was accomplished to complete the objectives of a TRR.
Test Readiness Review | |
Entrance Criteria |
Success Criteria |
|
|
b. The SAR is held late in the fabrication, assembly, integration, and test phase.
c. Entrance Criteria. Prior to the execution of the SAR, the activities and products identified in Table G-7 should be completed and documentation provided to all participants prior to the review.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-7 was accomplished to complete the objectives of the SAR.
System Acceptance Review | |
Entrance Criteria |
Success Criteria |
|
|
b. The FRR is held after the system has been configured for flight.
c. Entrance Criteria. Prior to the execution of the FRR, the activities and products identified in Table G-8 should be completed and documentation provided to all participants prior to the review.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-8 was accomplished to complete the objectives of the FRR:
Flight Readiness Review | |
Entrance Criteria |
Success Criteria |
|
|
a. The ORR examines the actual system characteristics and the procedures used in the system or product's operation and ensures that all system and support (flight and ground) hardware, software, personnel, procedures, and user documentation accurately reflects the deployed state of the system.
b. The ORR is held at the end of Phase D.
c. Entrance Criteria. Prior to the execution of the ORR, the activities and products identified in Table G-9 should be completed and documentation provided to all participants prior to the review.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-9 was accomplished to complete the objectives of the ORR.
Operational Readiness Review | |
Entrance Criteria |
Success Criteria |
|
|
Science and technology development conducted by NASA in BAR, ATD, and IP programs and projects may not be conducted along the same rigorous processes and schedules as FS&GS programs. Depending on the scope and technology readiness level (TRL) of these projects, a streamlined review system may be appropriate. (See NPR 7120.5 for a definition of TRL.) Sound engineering of processes defined in this SE NPR should be applied and reviewed when appropriate. A PTR review schedule with well-defined review entrance and success criteria should be developed in project formulation. Success criteria should ascertain whether sufficient technical maturity has been achieved to support a management decision to proceed to the next phase. In some cases, such as high TRL development efforts, a subset of FS&GS reviews is appropriate (e.g., SRR, PDR, CDR, SAR). PTRs should include both internal and independent external reviewers. Finding and actions from each PRT should be disseminated and resolved after each review.
a. The purpose of the DR is to confirm the decision to terminate or decommission the system and assess the readiness for the safe decommissioning and disposal of system assets.
b. The DR is normally held near the end of routine mission operations upon accomplishment of planned mission objectives. It may be advanced if some unplanned event gives rise to a need to prematurely terminate the mission, or delayed if operational life is extended to permit additional investigations.
c. Entrance Criteria. Prior to the execution of the DR, the activities and products identified in Table G-10 should be completed and documentation provided to all participants prior to the review.
d. Success Criteria. The review board was able to conclude that the success criteria in Table G-10 was accomplished to complete the objectives of the DR.
Decommissioning Review | |
Entrance Criteria |
Success Criteria |
|
|
a. Peer reviews provide the technical insight essential to ensure product and process quality. Peer reviews are focused, in-depth technical reviews that support the evolving design and development of a product, including critical documentation or data packages. They are often, but not always, held as supporting reviews for technical reviews such as PDR and CDR. A purpose of the peer review is to add value and reduce risk through expert knowledge, infusion, confirmation of approach, identification of defects, and specific suggestions for product improvements.
b. The results of the engineering peer reviews (EPRs) comprise a key element of the review process. The results and issues that surface during these reviews are documented and reported out at the appropriate next higher element level.
c.The peer reviewers should be selected from outside the project, but they should have a similar technical background, and they should be selected for their skill and experience. Peer reviewers should be selected to have as their only concern the technical integrity and quality of the product. Peer reviews should be kept simple and informal. They should concentrate on a review of the documentation and minimize the viewgraph presentations. A "round-table" format rather than a stand-up presentation is preferred. The peer reviews should give the full technical picture of items being reviewed.d.Technical depth should be to a level that allows the review team to gain insight into the technical risks. Rules need to be established to ensure consistency in the peer review process. At the conclusion of the review, a report on the findings and actions must be distributed.
e.Peer reviews must be part of the contract for those projects where systems engineering is done out-of-house.
| TOC | Change History | Preface | Prologue | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | AppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | ALL | |
| NODIS Library | Program Formulation(7000s) | Search | |