| TOC | Change | Preface | Chp1 | Chp2 | Chp3 | Chp4 | Chp5 | Chp6 | Chp7 | Chp8 | Chp9 | Chp10 | Chp11 | Chp12 | AppdxA | AppdxB | AppdxC | AppdxD | AppdxE | AppdxF | AppdxG | AppdxH | AppdxI | Fig12-2 | FigC-6 | FigC-7 | FigC-8 | FigD-1 | FigD-2 | FigD-3 | FigD-4 | FigD-5 | FigD-6 | FigD-7 | FigD-8 | FigD-9 | FigD-10 | FigD-11 | FigD-12 | ALL |


CHAPTER 3. Facilities Maintenance Management


3.1 Chapter Scope

This chapter describes the concepts for and approach to facilities maintenance management within NASA. It describes a generic facilities maintenance management system based on proven techniques. It also provides the flexibility needed at each Center for NASA's diverse, high technology mission. The purposes of this chapter are as follows:

a. To present the methodology and value of sound facilities maintenance planning.

b. To present factors for consideration while developing a facilities maintenance organizational structure.

c. To describe the functional relationships in a facilities maintenance management system.

d. To explain methods of analyzing maintenance functions and their relationship to planning and work performance.

3.1.1. Benefits of a Facilities Maintenance Management System

3.1.1.1. A facilities maintenance management system provides for integrated processes giving managers control over the maintenance of all facilities and collateral equipment from acquisition to disposal. The management system should provide at least the following:

a. Address all resources involved.

b. Accommodate all methods of work accomplishment.

c. Effectively interface and communicate with related and supporting systems ranging from work generation through work performance and evaluation.

d. Support each customer's mission.

e. Ensure communication with each customer.

f. Provide feedback information for analysis.

g. Reduce costs through effective maintenance planning.

h. Provide a system for accumulation of historical facilities maintenance data.

3.1.1.2. The goal is to optimize the employment of scarce resources (workforce, equipment, material, and funds) to maintain the facilities and collateral equipment needed to support the Center's mission in a safe and efficient manner. An effective facilities maintenance management system maximizes the useful life of facilities and equipment, ensures safety of facilities and systems, minimizes unplanned downtime, and provides an improved work environment within a given resource level. It also produces information for management decisions.

3.1.2. Functional versus Organizational Approach

3.1.2.1. Traditionally, the guidance presented in facilities maintenance procedures guides and manuals has been based on a standard organization. That approach does not recognize the diversity in mission and site conditions found among the NASA Centers. This procedures guide adopts a functional approach to facilities maintenance. The thrust is to identify those functions and processes required to provide an effective facilities maintenance program without specifying an organizational structure.

3.1.2.2. The discussion that follows covers maintenance management controls, maintenance management concepts, maintenance-related functions and processes, and other factors for consideration in establishing a facilities maintenance organization. The process for establishing the organization must accommodate Center-unique requirements and conditions.

3.1.3. Mission/Customer versus Condition Approach

3.1.3.1. Facilities maintenance normally is regarded as the total responsibility of the facilities maintenance manager who determines with what and when to accomplish maintenance based upon the physical condition of the facilities and appropriate maintenance practices. With limited resources, however, the facilities maintenance manager should work with the customer to provide quality facilities maintenance services as required to support the customer's mission. The facilities maintenance manager should coordinate with the customer in developing attainable solutions to facilities maintenance-related mission-support problems.

3.1.3.2. Facilities maintenance decisions such as whether to accomplish work now or defer it require a knowledge and understanding of the present and future need for the facility under consideration, as well as the economic and safety impact associated with those facilities. Thus, the facilities maintenance manager must maintain perspective in evaluating necessary maintenance requirements and in considering mission criticality and the need for preserving deteriorating facilities. Both mission and customer inputs are integral components of the facilities maintenance system.

3.2 Facilities Maintenance Functions

3.2.1. Facilities maintenance may be described as a number of interrelated functions and processes that directly or indirectly lead to the accomplishment of facilities maintenance work. Those that are not accomplished by the facilities maintenance organization are outside the responsibility of the primary users of thes requirements. This may also be the case when the scope of the work exceeds applicable facilities maintenance funding or resource thresholds (e.g., CoF projects). However, all functions are listed to ensure that all related services are considered when establishing a facilities maintenance organization and management system.

3.2.2. The following lists the major functions related to managing facilities maintenance. The relationships among the following major functions are depicted in Figure 3-1, Whole Maintenance Universe, along with the information flow and internal communication required:

a. Manage facilities and equipment.

b. Provide utilities services.

c. Employ and manage contracts.

d. Maintain building environment.

e. Manage material and tools.

f. Develop budgets and perform cost analyses.

g. Manage information resources.

h. Provide logistics support.

i. Maintain organizational interfaces.

3.2.3. The functions at the core of the whole maintenance universe reside in the Centers maintenance organization. They are the functions forming the day-to-day facilities maintenance operations and responsibilities. The maintenance organization's management is described in this chapter and its maintenance execution in Chapter 5, Facilities Maintenance Execution. The support functions in Figure 3-1 shown outside the maintenance organization are described in the following paragraphs:

3.2.3.1. Develop Budgets and Perform Cost Analyses. Although the maintenance organization performs cost analyses and develops a budget (POP) request, it is only an input to the Center and Agency's budget development. See paragraph 2.5, Facilities Maintenance Budget, for the maintenance organization's budget development.

3.2.3.2. Manage Information Resources. There are a number of information resources in other organizations supporting the maintenance organization. Personnel, cost accounting and similar staffs are required to manage a Center's maintenance operation. Of course a major function in the maintenance organization is the management of its information systems, such as its CMMS (see Chapter 6, Facilities Maintenance Management Automation).

3.2.3.3. Provide Logistics Support. A maintenance organization requires logistical support for functions such as mobile equipment (particularly large specialized items), transportation, and vehicle fuel. The maintenance organization may maintain a small warehouse for supplies and parts commonly used in its operations. Additional parts and supply support is required from the Center's logistics organization.

3.2.3.4. Maintain Organizational Interfaces. A major part of a maintenance organization's operation is its interfaces with other organizations. Working relationships and procedures must be established to assure that facilities maintenance functions are performed in an efficient and economical manner to meet Center requirements. These requirements include safety, legal, training, security, environmental, and specific requirements received in the form of Trouble Calls (TC), service requests, and similar requests.


Figure 3-1 Whole Maintenance Universe.


3.3 Management of Facilities Maintenance Program

3.3.1. Maintenance at NASA Centers is more than just repairing a leaking pipe or restoring power. It involves the coordinated effort of many talented people to ensure that facilities are in the best possible condition to support the Center's mission. To accomplish this the maintenance program must be managed to provide the maximum benefits from the available resources without waste.

3.3.2. A CMMS is an integral component of a Centers' facilities maintenance management operations. This automated system is designed to assist facilities maintenance managers in work reception, work planning, work control, work performance, work evaluation, and work reporting. This system, discussed in Chapter 6, Facilities Maintenance Management Automation, is usually linked to other database systems, such as Integrated Asset Program Management (IAPM), material management, and personnel management.

3.3.3. Figure 3-2 depicts the basic facilities maintenance management program. The program has four major aspects: Requirements Definition, Planning, Execution, and Analysis. Requirements Definition includes analyzing facilities condition assessments and the Center's mission to identify, quantify, and document Center operation and maintenance requirements. The Planning and Execution sections of the figure are discussed in Chapters 4, Annual Work Plan, and 5, Facilities Maintenance Execution. Analysis is discussed in detail in paragraphs 3.11, Management Indicators, and 3.12, Management Analysis. The following paragraphs briefly describe Figure 3-2 in a clock-wise flow starting with requirements definition:

3.3.3.1. Requirements Definition

a. Facility Inventory. The facilities inventory is the cornerstone of facilities maintenance management. It provides the detailed identification of what is inspected, operated, and maintained. Without an accurate inventory, maintainable items may not receive required maintenance, and maintenance budgeting, planning, and scheduling cannot be effective. Note that the inventory is not static; it includes continuous updates based upon facility and equipment changes.

b. Recurring Maintenance. After identification of what is inspected, operated, and maintained, a Center's Reliability Centered Maintenance program starts with identifying recurring maintenance requirements utilizing the decision logic tree shown in Figure 7-1. The requirements must be derived from analyzing the Center's mission and facilities inventory and utilizing a well-established set of local standards. The standards used in assessing facilities and determining what recurring maintenance and operations effort is needed to maintain the Center at NASA's specified quality level must include statutory, regulatory, and compliance requirements. Requirements are continually updated to include new facilities and changes based on the RCM analysis of work data provided during the acceptance process, which sets the baseline (see Chapter 8, Reliability Centered Building and Equipment Acceptance).

Chart-Basic Facilities Maintenance Program

c. Nonrecurring Maintenance. Nonrecurring requirements are determined by facility condition assessments and analyzing historical data, current inventory and mission requirements. A part of nonrecurring work is facility repairs (breakdown maintenance), including facility TC's.

3.3.3.2. Planning

a. Priorities set by management based upon mission requirements are important considerations in determining what is to be accomplished and in what order. The 5-year Maintenance Plan (see paragraph 4.8, 5-year Facilities Maintenance Plan) is an invaluable reference for the budgeting process, providing the information needed to plan allocation of resources.

b. Upon receipt of the annual budget, the 5-year Maintenance Plan (including the maintenance organization's CoF work) is reviewed again, together with updated facility needs. Because resources are constrained and only a portion of the needed work may be accomplished, alternative funding is obtained where possible. The remaining required maintenance work that cannot be funded in the current fiscal year is added to the BMAR.

c. A result of the budget process and the review is the well-documented AWP that is discussed in Chapter 4, Annual Work Plan. The AWP is used to guide the majority of the day-to-day maintenance work. The AWP also serves as a baseline reference for the facilities maintenance manager when accommodating nonfacilities and newly identified facilities maintenance requirements.

d. Throughout the Planning process with the requirements, priority setting, 5-year Plan and AWP, a key and essential element is the requirements definition. In order for the planning to be effective and in concert with the goals of the Center there must be continual, two-way communication between the facilities maintenance manager and the Center staff. Proper direction will ensure that maintenance work is prioritized, planned, and performed in accordance with the Center's mission goals.

3.3.3.3. Execution

a. During execution (see Chapter 5, Facilities Maintenance Execution) the use of the AWP as a basis for work control helps to schedule work in a steady, efficient flow pattern. The nonfacilities maintenance requirements and newly identified requirements are handled by adjusting priorities and rearranging the work flow patterns as required.

b. In addition to performing maintenance and repair work, it is very important to document the work accomplished in the Center's CMMS. This documentation, as well as historical data entered in the CMMS, is essential when analyzing the work performed and in work planning.

3.3.3.4. Analysis. The Analysis section of the maintenance management program is often neglected. Proper analysis is an important management function to point out inefficiencies and ways to better execute maintenance requirements by using alternative procedures and avoiding waste. Also, analysis may identify local standards that are overly stringent for mission needs or a priority system that requires "everything to be done yesterday," thereby interrupting scheduled work unnecessarily.

3.4 System Concepts

In creating an organization and system to perform facilities maintenance, the concepts discussed in the following paragraphs should be applied in implementing the basic maintenance program depicted in Figure 3-2.

3.4.1. Separation of Functions. The responsibility for generating, planning and estimating, and authorizing work should be separate from the responsibility for performing work. Similarly, it is preferable for the Quality Assurance functions to be the responsibility of an autonomous organization, apart from those ordering and performing the work. This provides the system with checks and balances and free of the appearance of conflict of interest.

3.4.2. Planning and Estimating. Work should be planned and estimated in enough detail to define the resources and tasks required to perform the work and to communicate this information to everyone involved. This information must be clear to customers, approving authorities, schedulers, material managers, and craft personnel.

3.4.3. Estimating Standards. Estimating standards should be the basis for work planning and estimating to permit realistic resource allocation, scheduling, work performance, and evaluation. Several commercial, industrial, and governmental standards are available to assist in work-order estimating. Chapter 10, Facilities Maintenance Standards and Actions, provides information on estimating standards.

3.4.4. Workforce Load Planning. Work planning should provide a sufficient volume of work sufficiently in advance of the required completion date to permit balancing the facilities maintenance workload among the shops, acquiring material, arranging timely contract support, achieving priorities, and coordinating all the elements. Work should be planned on at least a quarterly basis.

3.4.5. Continuous Inspection. A program for the periodic inspection of facilities and collateral equipment should on a timely basis identify facilities condition, maintenance deficiencies, work required, and changing conditions. PT&I and Facilities Condition Assessment methods should be part of the continuous inspection program. Chapter 10, Facilities Maintenance Standards and Actions, provides detailed information on continuous inspection and condition assessment.

3.4.6. 5-year Facilities Maintenance Plan. Centers should develop long-range facilities maintenance plans covering both level-of-effort and specific or one-time work requirements. These plans should reflect the total maintenance requirements and their prioritization in support of Center mission needs. Such management planning requires developing and justifying resource requirements on a multiyear basis. Centers must prepare both 5-year Facilities Maintenance Plans and AWP's. Chapter 4, Annual Work Plan, provides information on both of these plans.

3.4.7. Work Grouping

a. Personnel performing TC's, small Service Requests, and small repair jobs should be organizationally separated from personnel performing large facilities maintenance projects when possible. Twenty hours of effort is a suggested upper limit on the scope of these small jobs. Assigning these small jobs to a single shop avoids interrupting the workforce devoted to PM, PT&I, PGM, and larger repair jobs. The organization of the shops or groupings within a given shop should be based on factors such as work volume, geographic proximity, availability of transportation, materials and craft mix.

b. Work grouping also allows crafts personnel to productively complete small jobs by "batching" (i.e., providing crafts personnel with multiple TC's at once, grouping work in a particular building or area, or providing transportation with commonly used tools and materials). This reduces indirect time associated with processing small jobs (such as travel time or getting tools, equipment, and materials).

3.4.8. Work Scheduling. Work should be scheduled in an orderly manner considering safety, customer requirements, time constraints, material and tool/equipment availability, priority, workforce availability, and work-site availability along with necessary equipment or utility outages.

3.4.9. Work Status. The CMMS should include reporting systems that provide facilities maintenance managers the status of all work and any significant problems so they may take timely corrective action. Chapter 6, Facilities Maintenance Management Automation, discusses the use of CMMS.

3.4.10. Quality Assurance (QA). Both Government- and contractor-performed work should be subject to inspections for quality. Quality control is the contractor's (or civil service, if applicable) program in place to ensure that the product or service meets the quality requirements of the specification or work order. Quality assurance is the Government's program that validates the product or service quality and, by extension, ensures that an effective quality control program is in place and is performing as previously approved by the Government. In performance-based contracts, written QA plans must be prepared to guide these inspections and should be an integral part of all maintenance work. See Chapter 12, Contract Support, for detailed information on Quality Assurance Plans.

3.4.11. Condition Assessment/BMAR. The continuous assessment of the condition of facilities and collateral equipment coupled with the current BMAR defines the major portion of that total maintenance required to bring facilities up to NASA safety and condition standards. When evaluated with respect to a Center's safety and its mission requirements, the BMAR is a key element in management planning, budgeting, and allocating facilities maintenance resources. This process is discussed in Chapters 9, Backlog of Maintenance and Repair, and 10, Facilities Maintenance Standards and Actions.

3.5 Factors Affecting Facilities Maintenance Organizations

3.5.1. Physical Characteristics. The physical characteristics of a Center such as size, geographical distribution, climate, equipment, architectural style, and construction materials have a significant impact on the facilities maintenance organization. They directly affect the need for central shop spaces, remote job sites, travel time, special facilities maintenance equipment, and facilities maintenance standards.

3.5.2. Mission. The mission of a Center influences the facilities maintenance organization because it determines the facilities maintenance standards, the equipment mix, the workforce skill mix, work priorities, acceptable planned and unplanned down time, and resource levels. The maintenance organization must be structured to respond to the Center's mission.

3.5.3. Workforce Composition. Workforce composition is driven in large part by the Center's mission and physical characteristics. It affects the organizational structure and the division between contract and Government workforces. For example, a workforce with a large number of electricians and Air Conditioning (A/C) mechanics may dictate an organization with a separate shop for each craft. With a small workforce, these crafts may be in one shop.

3.6 Organization and Staffing

3.6.1. Organizational Considerations. Organizations plan, organize, perform, control, and evaluate work. The factors in the following paragraphs are important considerations when designing the organizational structure.

3.6.1.1. Contract Versus In-house. The proportion of the facilities maintenance work accomplished by support contractors significantly impacts the organizational structure. As the contracted portion increases, the Government workforce becomes more involved in contract administration and surveillance. The optimum mix of support contractor and Government personnel should be based on local conditions and priorities and should be consistent with the guidance contained in OMB Circular A-76. The principles of sound facilities maintenance management apply equally to in-house and contract work. In NASA Centers utilizing a maintenance support contractor the contractor is a key partner in implementing and operating a successful maintenance management program.

3.6.1.2. Labor Agreements. Labor agreements may dictate certain procedures, practices, consultations, and other action. These influence the organizational structure and the Government's flexibility in making changes to the organization, work methods, or work assignments. The human resources department may provide assistance in this area.

3.6.1.3. Functional Lines. The facilities maintenance functions are vital in support of the Center's mission. Where more than one organization has responsibility for performing facilities maintenance, close coordination is necessary. The facilities maintenance organization interfaces closely, with potential for overlap, with related processes such as master planning, major facilities acquisition, and transportation and utilities management. It may be logical to organize along functional lines; however, care must be taken to ensure that lines of communication are open and maintained among all related functions and organizational elements. Senior managers should encourage communication and liaison at all levels.

3.6.2. Staffing Considerations. A number of factors will influence the staffing of a facilities maintenance organization. In cases where a PBC is utilized to perform the facilities maintenance functions, the contractor is responsible for determining the staffing and skill mix of the workforce to meet the contractual requirements. The Center human resources department may provide advice in staffing matters. The following factors apply to staffing plan development:

3.6.2.1. Workload Balance. The facilities maintenance organization staffing should match the workload characteristics. The manpower resources available in each craft should closely match the amount of work included in the AWP taking into consideration work priorities and alternative methods of accomplishment. Consider using temporary or part-time employees or one-time contracts to accomplish seasonal, surge, intermittent, or one-time work requirements.

3.6.2.2. Education and Training. The facilities maintenance organization must ensure that personnel have and maintain the skills needed to cope with changing technology to effectively carry out the facilities maintenance program. Skill requirements are identified through periodic reviews of all the organization workload. Comparing skill requirements with the assigned personnel skill inventory will identify shortages for correction through education, training, recruiting, or other action. Skill inventories and requirements identification should address all facilities maintenance program phases, including shop crafts, administrative skills, PT&I technologies, and the use of computers.

a. As an example, training plays a major role in reaching and maintaining skill levels required for an effective RCM program. The training should be both of a general nature and technology/equipment specific. Management and supervisory personnel benefit from training which presents an overview of the RCM process, its goals, and methods. Technician and engineer training should include the training on specific equipment and technologies, RCM analysis, and PT&I methods.

b. RCM training is available from professional organizations, consultants, equipment manufacturers, and vendors. The following are examples of specific areas of training and possible sources for the training:

(1) Infrared Thermography (IRT) is complex and difficult to measure and analyze. Training is available through infrared imaging system manufacturers and vendors.

(2) Vibration monitoring and analysis training is available from equipment vendors. The Vibration Institute has published certification guidelines.

(3) Electricians, electrical technicians, and engineers should be trained in electrical PT&I techniques such as motor current signature analysis, motor circuit analysis, complex phase impedance, and insulation resistance readings and analysis. Equipment manufacturers and consultants specializing in electrical testing techniques provide classroom training and seminars to teach these techniques.

3.6.2.3. Licenses, Permits, and Certifications

The license, permit, or certification requirements in the following paragraphs are applicable to Government employees and contractors. When work requiring licenses, permits, or certifications is included in a contract, the contract must clearly state that the contractor should obtain all applicable NASA, State, and/or local government, licenses, permits, or certifications before performing the work.

a. Specialized personnel and facilities often are required to have licenses, permits, or certifications. These requirements apply to central utility plant personnel and to environmentally or safety sensitive facilities. To the maximum extent possible, such licenses, permits, and certificates should be issued by the State or local government rather than by Centers to avoid administrative duplication. Centers should issue only those licenses, permits, and certificates that are NASA-unique and, therefore, not available through other existing regulatory organizations. Detailed training and certifications requirements may be found in specific safety standards, e.g., NSS/GO-1740.9, NASA Safety Standard for Lifting Devices and Equipment, or NSS 1740.12, NASA Safety Standard for Explosives, Propellants, and Pyrotechnics. Additional hazardous operation safety certification requirements may be designated by each Center safety official or designee, but must include the minimum as listed in Chapter 4 of NPR 8715.3, NASA Safety Manual.

b. Central utility plant operators, such as at water treatment plants, boiler plants, and wastewater treatment plants, should be licensed by applicable State and local governments. Also, when required by State or local governments, permits for such things as incinerators, licenses for other facilities maintenance-related operations such as pest control and herbicide applicators, and certificates for equipment such as pressure vessels, lifting devices, and elevators must be obtained.

3.7 Customer Relations

Everyone who works at or uses Center facilities is a customer of the facilities maintenance organization. Some are direct customers, requesting and receiving specific services such as TC's or Service Requests. Others are indirect customers, using the facilities and collateral equipment such as HVAC systems maintained by the facilities maintenance organization. Facilities maintenance, which provides institutional , as well as program support, plays a major role in keeping these customers satisfied. This does not occur automatically. Customer relations should be a primary consideration in all facilities maintenance decisions. Facilities maintenance may be the key factor in developing and maintaining the professional reputation of Center institutional managers.

3.7.1. Communication

3.7.1.1. The facilities maintenance organization cannot operate effectively without open communication. Communication is extremely important within the organization to ensure coordination of competing resources. Communication with customers and other Center entities is absolutely necessary to ensure that the correct work is accomplished at the correct time and within allocated resources. Communications between the maintenance organization and their customers must be an integral part of the CMMS. The system should provide for customer access to submit requirements and for the customer to obtain current status of their request from submittal through completion. Day-to-day communications may also utilize other Center electronic means, including e-mail and home page access. Facilities maintenance personnel must be alert to the following barriers to communication:

a. Cryptic, incomplete work requests.

b. Misinterpreting the scope of work specified as "the supervisor wants".

c. Customers' misinterpreting technical answers to their questions on project status.

d. Differing understandings of mission needs.

3.7.1.2. Two-way communication must be encouraged, with the customer articulating customer desires and the maintenance organization providing constructive and continuous feedback through the CMMS or other electronic systems, including e-mail, where possible. This may provide an early warning of changes in workload and identify potential problems. It facilitates orderly workload planning by the facilities maintenance organization and its customers. This is particularly important during periods of limited funding because the maintenance organization often may help a customer translate desires into realistic facilities requirements, thereby obtaining an optimum solution or at least an adequate solution within the resources available. A well-informed maintenance organization and a "maintenance informed" Center is in a much better position to produce necessary results within available resources.

3.7.1.3. The reputation of the facilities maintenance organization is built as much on perception as on performance. A positive image of the facilities maintenance organization is created by proactive communications; i.e., keeping the customer informed about the status of the work, responding quickly to the requests, informing the customer in advance about the cost of the work, and reflecting the costs accurately in reimbursable billings and reports. The maintenance organization should have a customer liaison representative to work with each customer organization. The customer liaison should participate in the development of Memoranda of Agreement (MOA), AWP's, funding plans, and in the day-to-day support of the customer. However, every member of the facilities maintenance organization is an ambassador for the organization and should be sensitive to each customer's needs and perceptions.

3.7.1.4. The maintenance organization must have open communications with personnel and organizations such as the following:

a. Customers.

b. Health and safety.

c. Environmental office and agencies.

d. Engineering.

e. Mission personnel.

f. Center planners.

g. Support contractors.

h. Resource management personnel.

i. Local, State, and Federal regulatory agencies.

j. Headquarters NASA administrative and support offices.

3.7.2. Funding Sources. The facilities maintenance organization may find that a significant portion of its work is customer funded. This is especially the case with Service Requests and work directly supporting R&D programs. In establishing the organizational structure, the variability, time phasing, and duration of customer-funded work should be considered. Provision should be made for estimating and managing customer-funded work. Where the level of customer-funded work is variable or cyclical, use of contracts or temporary workers may be desirable to accommodate peaks and valleys in the workload.

3.7.3. Customer Mission. Customer relations should facilitate accomplishing the specific job that the customer requested. It includes understanding the customer's mission requirements and using this understanding to communicate with the customer and guide the customer's expectations. Thus, the facilities maintenance organization should understand the mission of each of its customers. This understanding will lead to better resource allocation decisions, enable the organization to meet each customer's needs, and improve the facilities maintenance organization's credibility by meeting real needs within the time and other resources available. Actually, the facilities maintenance organizations real mission is to support the Center mission utilizing the most cost-effective means available.

3.7.4. Memoranda of Agreement (MOA)

3.7.4.1. MOA's and other formalized agreements spell out support agreements between organizations and agencies. MOA's may cover agreements between the facilities maintenance organization and other Center departments, other Federal agencies, or local governments. Typically, MOA's outline details of services provided and funding responsibilities. It is possible for a Center to be both a receiver of services from, and a provider of services to, another organization. These services may be provided on a reimbursable or nonreimbursable basis. Examples include provision of utilities, shared use of operational facilities such as runways, provision of fire protection services, and maintenance of special facilities such as aviation fueling systems. Examples of MOA's from other Federal agencies are training and support from the Navy and General Services Administration (GSA).

3.7.4.2. MOA's may offer significant advantages through better use of facilities and avoid duplication of effort. The facilities maintenance organization should be alert for opportunities to use MOA's. Where services are available under an MOA, the facilities maintenance organization would not need to dedicate organizational resources to provide the service. The increased scope of the combined service may make it possible for the provider to perform the service at a reduced unit cost to all customers by realizing economies of scale. Properly managed, the increased scope also may provide flexibility and increased capability during a time of emergency. An assessment of the impact of MOA's should be made while developing AWP's.

3.8 Interfaces with Other Support Organizations

Facilities and equipment maintenance program effectiveness often depends on the support provided by other Center organizations. For example, the Comptroller may prepare budgets and allocate funds, the Human Resources Office may control staffing, the Procurement Office may handle requests for material, and the Administrative Office may handle reproduction and correspondence services. Responsibility for facilities planning and engineering, including major facilities and equipment acquisition, may rest with a separate organization such as Facilities Engineering. Essential services such as utilities may be purchased commercially or provided by a separate Government or host activity. The facilities maintenance organization should maintain close communication and cooperation with other supporting organizations, working together to plan and manage the workload.

3.8.1. Safety. It is NASA policy to "Avoid loss of life, personal injury or illness, property loss or damage, or environmental harm from any of its activities and ensure safe and healthful conditions for persons working at or visiting NASA facilities" (Appendix B, resource 13). To accomplish this, all individuals must act responsibly in matters of safety. The Center facilities maintenance organization is responsible for their role in safety by maintaining facilities in a safe condition and by performing tasks in a safe manner in accordance with NASA policy.

3.8.2. Environmental Compliance. Although environmental compliance is not typically one of the primary responsibilities of the Center facilities maintenance organization, virtually every facilities maintenance action has a potential impact on the environment. For this reason, facilities maintenance personnel must be knowledgeable about environmental requirements, adhere to applicable environmental rules and regulations, become involved to the limit of their responsibilities, and maintain open communication links with cognizant NASA environmental protection staff and regulatory officials. Environmental regulation compliance is a primary input item to establish standards.

3.8.3. Energy Management. The Center facilities maintenance organization is a prime participant in the Center's energy management program as developed in accordance with NPR 8570.1, Energy Efficiency and Water Conservation Techniques and Practices. The maintenance organization participates in identifying and is responsible for implementing O&M procedures and/or process improvements that are in the Center's Energy Efficiency and Water Conservation 5-year Plan. Responsible maintenance organization staff members help conduct energy audits. Analysis of the Center's Energy Management and Control Systems (EMCS) data must be included in the maintenance organization's planning to identify changes that indicate maintenance problems or imminent equipment or system breakdowns. All of this energy management program support must be integrated into the maintenance organization's AWP and 5-year Plan.

3.8.4. Contract Support

3.8.4.1. Much of the Center facilities maintenance work is performed by contract, either by separate, specific, one-time CoF contracts, specific facilities maintenance contracts (using non-CoF funds), or support services contracts. In the case of the specific, one-time contracts, the facilities maintenance organization's responsibility is limited to initial facilities maintenance and repair requirements identification, perhaps preliminary scope definition or cost estimate preparation, observing the facility's acceptance testing (as appropriate), acceptance of initial base line data, and resumption of the maintenance responsibility after the contract is complete. For facilities maintenance support services contracts, the facilities maintenance organization has a greater responsibility. It should be involved throughout the acquisition process in each of the following functions:

a. Determining the need for the contract.

b. Serving as a member of the acquisition team.

c. Drafting the acquisition schedule and milestones.

d. Preparing the needs analysis.

e. Writing the acquisition plan.

f. Writing the statement of work.

g. Assisting Procurement in determining the contract type.

h. Writing the quality assurance plan.

i. Conducting quality assurance surveillance during contract performance.

3.8.4.2. Close coordination with the cognizant procurement office is essential in obtaining quality services in a timely fashion. Additionally, emphasis should be placed on advance acquisition planning to ensure continuity of services.

3.9 Physical Plant Information

a. Initially the maintenance organization must know the facility activity status in order to establish a facility's maintenance requirement. The status may range from active to abandoned with each status requiring a different level of maintenance (see paragraph 3.9.1, Facility Activity Status).

b. Information describing the facilities and collateral equipment at a Center is essential for planning facilities maintenance actions, efficiently performing facilities maintenance, documenting maintenance histories, following up maintenance performance, energy reporting, and management reporting. Without this information, neglect of essential systems is likely, leading to inefficient operation, system failure, or loss of service.

c. With the increasing use of CMMS, obtaining the information in computer readable format is strongly recommended. Chapter 6, Facilities Maintenance Management Automation, addresses CMMS requirements and usage.

d. Complete physical plant information consists of several databases distinguished by the type of information they contain. Chapter 6, Facilities Maintenance Management Automation, discusses databases from the perspective of facilities maintenance management automation. The following paragraphs examine the physical plant information databases in terms of the type of information they contain.

3.9.1. Facility Activity Status. The following paragraphs are to provide insight into facility status classifications. Each status has its own level of maintenance required ranging from full maintenance for an active facility to no maintenance for a facility with an abandoned status. For detail information on maintenance requirements for each inactive facility status see NPR 8800.15, Real Estate Management Program Implementation Manual.

a. Active facility. Any facility that has a specific and present, or near term, program or institutional requirement. Space utilization would normally be at least 50-percent and/or the usage level exceeds 50-percent of the available time for use.

b. Inactive facility. Any facility that has no specific and present, or near-term, program or institutional requirement. The inactive facility may be placed in a "Standby," "Mothballed," or "Abandoned" status. The following generally applies to all levels of inactive facilities:

(1) No personnel occupy the facility.

(2) Utilities are curtailed, other than as required for fire, security, or safety.

(3) Facility is secured to prevent unauthorized access and injury to personnel.

(4) Facility does not receive funding for renewal, or other significant improvement.

(5) Reserved.

3.9.2. Descriptive Data

a. Descriptive data is the detailed identifying information on the items to be maintained. The data falls into the following two classes:

b. Each separately identified and maintained item may be part of a hierarchy of systems and subsystems. For example, a motor may be a component of the water circulating subsystem of an A/C system in a facility.

c. Descriptive data should identify items to their related systems and subsystems. The number of hierarchical levels depends on Center requirements, but four levels of system/subsystem is the suggested minimum. For equipment, the descriptive data should include the equipment classification or grouping.

3.9.2.1. Facilities. Table 3-1 provides a listing of descriptive factors and attributes used to develop a facilities database. This list is a suggested minimum for facilities management. The items on this list are generally self-explanatory.

Facility Number Material
Facility Title Finish
Location
Status
Inspection Cycle (Yrs)
PGM Checklist/Guide No.
Facility Component (e.g., Ceiling, Door, Floor,
Flashing, Wall, Drainage, Parapet)
Estimated Design Life (years)
Funding Source
Facility System (e.g., Exterior, Interior, Roof,
Tank, Fence, Grounds)
Construction Date
Condition Code

Table 3-1. Facilities Descriptive Data


3.9.2.2. Collateral Equipment. Table 3-2 is a list of descriptive factors and attributes used to develop a collateral equipment database. This list is a minimum for collateral equipment maintenance management. Centers with PT&I programs will have additional equipment data elements such as location of test points.

Inventory Number
Nomenclature
Location -
Building
Floor
Room
Zone
Manufacturer
Vendor/Supplier
Model
Serial Number
Date Acquired
Estimated Life
Cost
Size -
Capacity HP
Voltage Weight
Current Dimensions

Systems -
Major System
Subsystem
Major Component
Component
Classification
Use/User
Priority
Funding Source
PM Cycle Identifiers
PM Guide No.
Inspection Identifiers
Condition Code



Table 3-2. Collateral Equipment Descriptive Data


3.9.3. Drawings

3.9.3.1. Drawings and other graphic data are a significant portion of the physical plant information, especially for buildings, structures, utilities systems, real estate, and land improvements. They also may be a significant portion of the available information for equipment in the form of shop drawings, schematics, photographs, and assembly drawings. Drawings may exist in many forms, including paper, photographs (such as microfilm, microfiche, and aperture cards), video images, and computerized data. Computerized forms include Computer Aided Design and Drafting (CADD), Geographic Information Systems (GIS) or vector based drawings. Drawings may be linked to work orders through a CMMS database.

3.9.3.2. Significant challenges in drawing management include keeping drawings up to date, maintaining an indexed library of drawings, and maintaining a linkage between the drawings and the systems they represent. To the maximum extent possible, Centers should require all drawings for new or modified facilities and equipment to be delivered to the Government in computer readable and revisable form. However, the wholesale conversion of existing drawings to computerized form may not be practical. All drawings should be filed and retained in accordance with guidance provided in NPR1441.1, Records Retention Schedules.

3.10. Data Gathering

It is necessary to gather facilities and collateral equipment data to support the facilities maintenance program.

3.10.1. Existing Databases

3.10.1.1. Existing databases maintained by the Center provide a starting point for developing an inventory of maintainable facilities and collateral equipment items. However, databases developed for other purposes, such as financial accounting, will not identify all maintainable items, systems, subsystems, and components. Further, they may include items not relevant for facilities maintenance management purposes. Using these databases as a starting point requires screening entries for inclusion in the facilities maintenance database. Where a unified Center database exists, this might take the form of flagging records as part of the facilities maintenance management program. Where the existing data is in a computerized database, it also may be possible to arrange for electronic transfer of portions of the data. This may simplify loading the data into the facilities maintenance management database. Potential existing databases include the NASA Real Property Data System and Center-unique industrial plant, personal, and minor property or collateral equipment inventory systems.

3.10.1.2. Creation of separate databases with common data elements carries the risk of having conflicting data. If separate databases are created, a methodology must be developed and implemented to update the data from one database to the others to avoid inconsistencies.

3.10.2. Physical Inventory. A physical inventory may be necessary to verify the data imported from other databases and to gather supplemental information to identify maintainable items and their associated systems, subsystems, and components not previously inventoried. Identification tags placed on collateral equipment during the inventory will help to ensure that all maintainable collateral equipment is picked up for entry into the database. Using identification tags also helps to avoid duplication.

3.10.2.1. In-house. It is possible to perform a complete physical inventory using in-house forces as part of the continuous inspection and PM programs. However, this effort may take a long time and could result in the diversion of a significant portion of the facilities maintenance workforce, thereby adversely impacting routine facilities maintenance.

3.10.2.2. Contract. Contracting for the inventory is an effective method of obtaining the data. The contract may be a separate action, in conjunction with a comprehensive condition assessment, or it may be part of the development of Maintenance Support Information (MSI). For more information see paragraph 10.9, Maintenance Support Information (MSI).

3.10.2.3. Inventory Maintenance. Once developed, the facilities and collateral equipment inventory requires continuous updating to reflect additions, deletions, or changes to the physical plant. Normally, this effort is part of the continuing inspection program.

3.10.2.4. Identification Tags. Equipment identification tags should be clearly visible. Using permanent, machine-readable tags such as preprinted bar code labels eases maintenance and inventory automation and reduces the potential for data entry errors.

3.10.3. User Information. Equipment users or custodians also are a source of inventory information as they receive new equipment or determine that equipment they already have requires maintenance. The initial identification typically will take the form of a request for equipment installation or maintenance. It may also be a response to a call for inventory assistance from the facilities maintenance organization. In either case the information provided may not be enough for facilities maintenance management purposes. A field investigation may be necessary to obtain all of the maintenance information.

3.11. Management Indicators

a. Paragraph 3.11.1, Work Element Relationships, discusses the total facilities maintenance effort and relationships among the individual work element efforts. However, there are a number of other relationships typically used in the facilities maintenance community for indicating the effectiveness of the facilities maintenance operation and for comparing current performance with goals and objectives. These relationships are called management indicators, performance measures, or simply "metrics". Three ratios/indicators/metrics are shown in Table 3-3 as examples.

b. As shown in Figure 3-3, management indicators may be expressed as words (such as "outstanding" or "excellent") or numbers (metrics). Current management theory holds that one cannot manage an operation effectively unless one may measure it. Metrics are preferable to word descriptions because they may be trended more easily. Also, they tend to be more precise and objective than words. Regardless of what metrics are used by individual Centers, some system of measurement is vital to the process of continuous improvement.

c. It is NASA policy to continuously improve technical and managerial processes in order to minimize life-cycle maintenance and repair costs. One process to use is benchmarking. Using benchmarking and its related metrics Center facilities maintenance managers may evaluate maintenance performance, compare performance against maintenance standards and identify trends. This process will help managers in identifying and implementing "best practices" and provide a base for performance projections that may be used in preparing the AWP and the Center's 5-year plan.

d. The following paragraphs provide a general definition of a metric, its components, and its attributes. They also discuss the role metrics play in the continuous improvement processes and present examples of metrics used by facilities maintenance organizations.

Chart-Management Indicators

Figure 3.3. Management Indicators


3.11.1. Work Element Relationships

3.11.1.1. There are relationships among the facilities maintenance work elements that indicate the strengths and weaknesses of a facilities maintenance program. Table 3-3 shows typical ranges of effort for the principal work elements at a large physical plant of diverse age and complexity.

3.11.1.2. The percentages in Table 3-3 apply to the total facilities maintenance effort. The percentage ranges are guides only. For example, if repairs exceed 20-percent by a significant amount, it may indicate that more effort must be put into PM, PT&I, and PGM. Likewise, if TC's exceed 10-percent, it may indicate that PM and PT&I effort should be increased. The greatest effort, 50- to 60-percent, should be applied to PM, PT&I and PGM. The limit on Service Request work is suggested only because of the potential for a large amount of Service Request work to detract from the maintenance effort.

3.11.1.3. The ranges in Table 3-3 are recommended as a basis for self-evaluation until each Center accumulates sufficient data to reflect its unique situation. Thereafter, analysis should be based on the relationships appropriate to the Center.

3.11.1.4. Two of the work elements do not appear in Table 3-3: Central Utility Plant Maintenance and Operations and Grounds Care. Both depend on local circumstances and vary too widely to estimate a meaningful range.

Also, there are useful ratios that may be used to assess the quality of the facilities maintenance program. These are shown in Table 3-3. Trends in these three ratios indicate facilities maintenance performance. While absolute values cannot be assigned to these ratios, facilities maintenance managers should track the ratios and strive to maintain a downward trend.

Chart-Work Element Percentages and Indicators

Table 3-3. Work Element Percentages and Indicators


3.11.1.6. In the case of Ratio 1, the amount of CoF (construction and additions) and SR, both new work, is not controlled by the facilities maintenance organization. However, if the ratio is high and increasing, plant degradation may result. New work increases the CRV and the maintenance workload. Funds should increase proportionately to maintain the desired 2- to 4-percent-of-CRV funding level.

3.11.1.7. With respect to Ratio 2, the numerator may be controlled only within narrow limits. Also, the numerator is oriented toward correcting things that are broken. The opposite is true for the denominator. Management decides how much effort to expend on the denominator, which is preventive in nature because it minimizes future failures. There is an inverse correlation and a multiplier effect between the denominator and the numerator. As the denominator decreases, the numerator usually increases much faster. For example, failure to perform PM on a piece of equipment or system usually results in much more costly repair later on. A small change in the denominator, over time, causes a much larger opposite change in the numerator.

3.11.1.8. For Ratio 3, the trend should always be downward, toward the NASA goal of reducing the backlog to a manageable level.

3.11.1.9. As a general rule, the percent of work authorized by work order should increase, the percent of scheduled work should increase, and the percent of unscheduled work should decrease.

3.11.2. Metrics Definition

3.11.2.1. Metrics are meaningful measures. For a measure to be meaningful, it must present data that encourages the right action. The data must be customer oriented and be related to and support one or more organizational objectives. Metrics foster process understanding and motivate action to continually improve the way a process is performed. This is what sets metrics apart from measurement. Measurement does not necessarily result in process improvement. Effective metrics always will. Projecting this improvement, metrics may be used in preparing a Center's AWP and 5-year Plan.

3.11.2.2. A more useful definition for managers is that a metric is a measurement that is made repeatedly at prescribed intervals and that provides vital information to management about trends in the performance of a process or activity or in the use of a resource.

3.11.2.3. Each metric consists of a descriptor and a benchmark. A descriptor is a word description of the units used in the metric. A benchmark is a numerical value of the metric, or the limits within which the metric is to be kept, that management selects as the goal against which the measured value of the metric is compared. For example, a typical metric is the ratio of emergency work to total facilities maintenance work expressed as a percentage and shown in the following equation:

Emergency Work (hr) x 100 = %
Total Maintenance (hr)

3.11.2.4. The emergency work and total maintenance work are the descriptors, the units of which are hours. In the example, 2-percent is the goal, or benchmark.

3.11.3. Metrics Attributes

3.11.3.1. Metrics have common attributes that should be considered when they are being developed. A good metric has many of the following attributes:

a. It is customer oriented.

b. It is linked to a goal or objective.

c. It is process/action oriented.

d. It distinguishes good from bad or desirable from undesirable results.

e. It is derived from data that is readily collectable.

f. It is trendable.

g. It is repeatable.

h. It is simple.

i. It expresses realistic/achievable goals.

3.11.3.2. Customer orientation is important because the ultimate success of facilities maintenance services is partly dependent on how they are perceived by the customer. A metric should be action oriented, which means that the organization must have the capability to change the metric parameters. Just as one cannot manage effectively what one cannot measure, there is no need to measure what one cannot control. A metric should distinguish good from bad, which again is based on a standard or goal; i.e., movement toward the goal is good, and conversely, movement away from the goal is bad. The data for the metric should be collectable, preferably already contained within the accounting system or the CMMS. A metric must be trendable so that successive readings may be compared with meaningful results. It should be simple, so that those who use it, carry it out, or are affected by it may understand it. Finally, the metric must be realistic. If it is clearly not achievable, workers will not strive to achieve it.

3.11.4. Metrics Role in Continuous Improvement

3.11.4.1. Two organizations that promote the use of metrics for continual improvement are the American Productivity and Quality Council (APQC) and the American Society for Quality (ASQ). While the APQC's emphasis is on benchmarking, the ASQ promotes customer satisfaction as the means to achieve continuous improvement.

3.11.4.2.

3.11.4.3. When the metric is implemented, management should establish the baseline, i.e., where the organization is with respect to the benchmark. Preferably, this information is known, at least approximately, and used when setting the goal (benchmark). Then management must develop a system to measure and report the descriptor condition regularly over uniform periods of time (e.g., daily, weekly, monthly). The measured value is compared with the benchmark to identify the gap between the two. Management then acts to close the gap. After several iterations, it may become apparent that either the descriptor is not appropriate or the benchmark is unrealistic. If this is the case, the metric should be revised and a new baseline determined. If the original metric is both suitable and realistic, the measurement cycle should be repeated with the gap between the benchmark and the measured value becoming progressively smaller. In this situation, true continuous improvement is occurring.

Chart-Continuous Improvement Process

Figure 3-4. Continuous Improvement Process


3.11.5. Benchmarking. One of the best methods for achieving continuous facilities maintenance improvement is using metrics with benchmarking. Benchmarking is the process of continuously identifying, measuring, and comparing one's processes, products, or services against those of recognized leaders in order to achieve superior performance. The benchmarking process steps are shown in Figure 3-5.

3.11.5.1. Objectives. The objectives of benchmarking are as follows:

a. Accelerate the change process.

b. Achieve both incremental and breakthrough improvements.

c. Achieve greater customer satisfaction.

Chart-Benchmarking Process Steps

Figure 3-5. Benchmarking Process Steps


d. Learn from the best to avoid reinventing (applying lessons learned).

e. Apply best practices utilizing the latest feasible technology.

3.11.5.2. Types of Benchmarking

a. Internal. A comparison of internal operations; for example, within a Center or NASA-wide.

b. Competitive. A competitor-to-competitor functional comparison.

c. Functional. A comparison of similar functions within NASA Centers or with industry leaders.

d. Generic. A comparison of functions or processes that are the same regardless of Center or industry.

3.11.5.3. Approaches To Benchmarking. The NASA approach found to be successful has been generic benchmarking using the hybrid approach. Benchmarking approaches are as follows:

a. Centralized. Managed by a single corporate entity; e.g., by NASA Headquarters.

b. Decentralized. Managed at the local level; e.g., by individual Centers.

c. Hybrid. A combination of the centralized and decentralized approaches.

3.11.5.4. Benchmarking Procedures. Referring to the general steps shown in Figure 3-5, Benchmarking Process Steps, the benchmarking process should proceed as follows:

a. Develop a specific list of the functions that the maintenance organization does well and that may be offered to benchmarking partners as best practices.

b. Develop a specific list of the functions about which the maintenance organization is concerned; i.e., those that need improvement.

c. Identify specific companies, professional facilities maintenance associations, and facilities maintenance-related publications known to excel in the specific areas of concern.

d. Develop a questionnaire to obtain specific data about the functions the maintenance organization wishes to benchmark (concerns) and send it to the prospective benchmarking partners identified in paragraph 3.11.5.4.c.

e. Analyze the questionnaire responses to identify the best potential benchmarking partners.

f. Offer to benchmark with one or more of the organizations identified in paragraph 3.11.5.4.c. These organizations are the best potential benchmarking partners.

g. After benchmarking agreements have been reached, exchange lists of lessons learned, best practices, and concerns.

h. Suggest that the benchmarking partner select topics from the organization's lessons learned and best practices list for the organization to brief during the benchmarking visit. Further, ask partners to select topics from their list of concerns for the partners to brief to the organizations representatives during the benchmarking visit.

i. Exchange lists of written questions and general information such as organization charts for study at least 2 weeks prior to the benchmarking visit.

j. Arrange a mutually agreeable date for visiting the benchmarking partner.

k. Identify the points of contact for the briefings that both organizations will give so that the points of contact may coordinate and focus the presentations.

l. Develop a detailed visit agenda agreeable to both parties.

m. Observe the benchmarking code of conduct, illustrated in Table 3-4.

BENCHMARKING CODE OF CONDUCT



When Benchmarking, you will...

a. Consider legal implications.

b. Be willing to give the same type of information received.

c. Respect confidentiality.

d. Keep information nternal.

(1) Use benchmarking points of contact only.

(2) Do not refer benchmarking materials to third parties without permission.

(3) Understand the partner's expectations.

(4) Act in accordance with the expectations.

(5) Be forthright and forthcoming in discussions.

(6) Follow through with commitments.

Table 3-4. Benchmarking Code of Conduct


n. Offer reciprocal visits.

o. Document visit results.

p. Distribute the documentation of the visit results to the proper internal organizational elements for evaluation.

q. Develop implementation plans.

r. Develop lessons learned.

s. Share information and benchmarking experience with other NASA organizations.

t. Follow up for continuous improvement.

3.11.5.5. Facilities Maintenance Management Indicators

a. The benchmark depends upon the Center baseline and goal or objective. More important a specific metric by itself is the recognition of its usefulness in proactively establishing patterns, trends, and correlation with other data to describe past, current and anticipated conditions. Center maintenance managers should utilize metrics on a continual bases to evaluate the effectiveness of their management.

b. A major benefit of the metric information is its evaluation over several periods to obtain trends. Metrics may be maintained visually through the use of graphs, bar charts, or other methods. The periods of time may be monthly, quarterly, annually, or by contract evaluation period. The benchmark of "Local" means that the individual Center should establish its own benchmarks based upon experience and look for improvement trends and irregularities.

c. The metrics presented in Appendix F should be used by Center maintenance managers for evaluating various maintenance areas on a continual basis. Individual metrics may refer to the maintenance organization as a whole or by individual shops, crafts, contracts, or subcontracts. These are essentially tools for facilities maintenance managers in evaluation of their operations and for providing NASA Headquarters metrics data.

3.11.6. Examples

3.11.6.1. Center Metrics. Metrics may be classified using categories such as facility condition, work performance, work elements, budget execution, and many others. Examples shown in Table 3-5 are some of the metrics that are recommended for Center self assessments. These and additional metrics that might be utilized in evaluating a maintenance program and benchmarks are contained in Appendix F.

3.11.6.2. NASA Headquarters Metrics. Table 3-6 contains example NASA Headquarters Metrics. The Center's metrics data shown in the table is usually submitted to NASA headquarters in the December-January timeframe. The Following paragraphs provide additional insight into the metrics data shown in the table.

SAMPLE METRICS

FACILITY CONDITION
OTHER
Annual Maintenance Funding ($)
Current Replacement Value ($)
Backlog of Maintenance & Repair ($)
Current Replacement Value ($)
WORK PERFORMANCE
WORK ELEMENT
Jobs Completed as Scheduled (No.)
Total Jobs Scheduled (No.)
Preventive Maintenance ($)
Total Maintenance Cost ($)
Average Completion Time for
Routine Trouble Calls (hours)
Repair ($)
Total Maintenance Cost ($)
Average Completion Time for
Repairs (days)
Service Requests ($)
Total Maintenance Cost ($)
BUDGET
OTHER
To Date Expenditures ($)
Budget ($)
PM's Completed (No.)
Total PM's Scheduled (No.)

Note: Benchmarks for the metrics shown above are in Appendix F.


Table 3-5. Sample Center Management Metrics


a. BMAR. This item is the Center's estimated facilities maintenance and repair work that was not accomplished due to a lack of funds (deferred maintenance and repair). This estimate contains work that realistically would have been obligated if funding had been available.

b. Unconstrained Maintenance and Repair (M&R) Requirement (Without CoF). The maintenance and repair requirement includes PM, PT&I, ROI, PGM, non-CoF repair, and TC (facility repair only). This metric is the Center level funding amount that represents a reasonable manager's estimate of the full annual requirement that would maintain the Center's facility inventory in a "good commercial" level of condition. This amount of funding would not allow BMAR to grow further, and would provide a level of reliability that the supported programs find acceptable for their missions. A minor amount of BMAR reduction could be included in the figure. Note that this estimate is at the Center level thus including all facilities maintenance and repair regardless of fund source (except it does exclude CoF funds) or implementing organization. The estimate used should be one that realistically could have been obligated if funding had been available.

CENTER FACILITIES MAINTENANCE PERFORMANCE METRICS

BMAR ($M)
Unconstrained M&R Requirement (Without CoF) 1 & 5 ($M)
Initial Operating Plan for M&R 1 FYXX ($M)
Annual M&R Funding (Without CoF) 1 ($M)
Cost of Scheduled Work 2 ($M)
Number of PT&I "Finds" (#)
FYXX Total Site CRV ($B)
Cost of Significant Failures from Constrained Resources 3
Cost of Significant Failures Avoided Using PT&I 4

CALCULATED BY NASA HEADQUARTERS FROM DATA ABOVE

PM and PT&I Completed (#)
PM and PT&I Scheduled (#)
Breakdown Repair Cost ($)
Total Maintenance & Repair 1 Cost ($)
Scheduled Maintenance Dollars ($.)
Total Maintenance Dollars ($)
Breakdown Repair Dollars ($)
Total Maintenance Dollars ($)
Backlog of Maintenance & Repair 1 ($)
Current Replacement Value ($)
Unconstrained Maintenance & Repair 1 ($)
Current Replacement Value ($)
Institutional Operating Plan ($)
Current Replacement Value ($)
Maintenance & Repair 1 Funding ($)- -
Current Replacement Value ($)
  1. Annual Maintenance & Repair (M&R) funding consisting of PM, PT&I, ROI, PGM, non-CoF repair, and facility repair TC.

  2. Scheduled Work consisting of PM, PT&I, ROI, PGM, and PT&I "Finds" repair costs.

  3. Due to or influenced by constrained resources (Includes direct repair costs and other Center cost impacts.)

  4. Includes reduced repair costs and other Center cost impacts that were avoided by use of PT&I.

  5. The Center level funding amount that represents a reasonable manager's estimate of the full annual requirement that would maintain the Center's facility inventory in a "good commercial" level of condition, while not allowing BMAR to grow further, and providing a level of reliability that the supported programs find acceptable for their missions. A minor amount of BMAR reduction could be included in this figure.

Table 3-6. Example of NASA Headquarters Management Metrics


c. Initial Operating Plan for M&R. This is the Center's M&R funding from all sources (except CoF) included in its initial submittal for the fiscal year following the fiscal year covered by the metrics summary.

d. Annual M&R Funding (Without CoF). This is the actual Center M&R funding from all sources (except CoF) for the fiscal year covered by the metrics summary.

e. Cost of Scheduled Work. This is the actual cost of scheduled PM, PT&I, PGM, ROI work and actual PT&I "Finds" repair work during the fiscal year covered by the metrics summary.

f. Number of PT&I "Finds". This is the actual number of "Finds" (impending failure or degrading condition) discovered utilizing the Center's PT&I testing program during the fiscal year covered by the metrics summary.

g. Total Site CRV. This is the Center's CRV for the fiscal year covered by the metrics summary.

h. Cost of Significant Failures from Constrained Resources. This is the cost of significant failures that occurred due to or influenced by funding restraints. This cost includes direct repair cost and other Center cost due to the failure(s). This item would, as an example, include equipment repair/replacement cost and the additional cost associated with a test scrub or delay if the equipment failure was due to a lack of maintenance funding.

i. Cost of Significant Failures Avoided Using PT&I. This is an estimate of significant cost avoided because of the use of PT&I. The cost avoided would include reduced repair cost and other Center cost impacts avoided because of the use of PT&I.

3.12. Management Analysis

The maintenance requirements at each of the NASA Centers change continually as does the maintenance technology. As a result, maintenance programs should be analyzed periodically at both micro and macro levels by facilities maintenance managers. These analyses should be based on personal observations of work being performed, customer feedback, reports (informal and formal) supervisor evaluation, metrics evaluations, and reports from the CMMS.

3.12.1. Performance Review

3.12.1.1. Facilities maintenance managers should review the performance indicators periodically to evaluate progress and readjust the maintenance program. Performance reviews may be formal or informal, based on the needs of the organization and the personal style of the manager. The manager analyzes the information contained in the metrics and, when available, the information provided through benchmarking. The manager's performance reviews should consider how to improve the way of doing business rather than continuing to operate in the old ways. The lessons learned from benchmarking are often helpful in determining the actions that should be taken as a result of performance reviews.

3.12.1.2. The following are candidate areas to review:

a. Standards of maintenance may require modification because of changing mission requirements or changes in the use of facilities.

b. New maintenance techniques or materials may provide savings, thereby enabling additional work to be accomplished within the same level of resources.

c. Initial priorities may be set higher than necessary because of incorrect perceptions, lack of management preparation, and/or lack of insight, which may result in expediting work unnecessarily. This, in turn, may lead to worker inefficiency and extra management and supervisory effort.

3.12.2. Cost Avoidance

3.12.2.1. Cost avoidance opportunities are not always obvious from the day-to-day observation of maintenance operations. When looking at the costs to maintain or repair a facility, the manager and all maintenance personnel should consider measures to avoid facility damage or equipment breakdown. Cost avoidance action seeks to eliminate all maintenance efforts resulting from inefficiencies, misdirection, and mismanagement. Also, customers must recognize their role in optimizing the expenditure of maintenance funds.

3.12.2.2. The following are factors that should be considered in identifying cost avoidance measures:

a. Preventing facility damage.

b. Minimizing wear and tear on facilities.

c. Eliminating the waste of energy.

d. Recognizing opportunities for multiple use or ways to reuse excess or underutilized facilities.

e. Eliminating, containing, or controlling hazardous material contamination with its consequent impact on the use of facilities.

3.12.2.3. These are not new ideas, and most individuals take reasonable care of the facilities they use. However, waste may result when proper consideration is not given to the care and use of facility assets.

3.12.3. Productivity Enhancements

3.12.3.1. Facilities maintenance productivity may be enhanced by actions such as the following:

a. Improving customer feedback to reduce customer calls to management for information.

b. Using a priority system that enables workers to complete one job before starting another.

c. Empowering maintenance personnel to report problems when found and changes to facilities or equipment otherwise not known (e.g. customer-made changes).

d. Reviewing data entry procedures to ensure that different personnel do not enter data several times into different systems.

e. Reviewing work order execution times to identify wasted manpower caused by material, transportation, or support delays.

f. Monitoring to look for improved scheduling and travel consolidation efficiencies.

3.12.3.2. Two major detriments to productivity enhancements are excessive reporting without reason and the natural tendency to resist change.

3.12.3.3. One of the most important productivity enhancers is keeping personnel well motivated and encouraging a sense of ownership toward the facilities. This applies for both Government and contractor personnel.

3.12.4. Alternative Procedures. Maintenance and repair work does not decrease when resources are scarce. On the contrary, more items tend to be deferred, and the maintenance problems grow worse. Accordingly, efforts must be devoted to finding alternative methods to accomplish the same results. The following should be considered:

a. PT&I technology with remote sensing of equipment status replacing periodic, on-site manual inspection and reporting.

b. Increasing PM crew capabilities to reduce the number of separate crews required to perform maintenance on a particular item of equipment.

c. Replacing scheduled PMs with PT&I schedules.

d. Process Improvement/Reengineering.

3.12.5. AWP Monitoring. The program analysis depicted in Figure 3-2 not only refers to management indicators but also refers to the AWP since it is the baseline or guide for the year's work. The plan should be updated with new information as appropriate. The following questions should be asked when comparing actual performance with the AWP:

a. Is the organization within budget?

b. What is the cause of any budget variances?

c. Is scheduled maintenance being performed on schedule?

d. Should Reliability Centered Maintenance (RCM) root-cause analysis be applied to any identified problem?

e. Were there any significant emergencies?f. Is productivity improving? Is it being hampered by institutional factors?

g. Have there been any mission changes affecting facilities?

h. Has there been any customer changes affecting facilities?

i. What customer feedback has been received?

3.12.6. Performance Indicator Use

3.12.6.1. The performance indicators discussed in paragraph 3.11, Management Indicators, are only beneficial when they are analyzed by management for use in improving the total program. These may be broken down into internal and external indicators as follows:

a. Internal indicators are those where the information is all directly available to the facilities maintenance manager, and the indicators assist the manager in improving operations. A sample of these indicators is shown in Table 3-7. Most of these indicators evaluate timeliness, efficiency, and maintenance effectiveness.

b. External indicators are based on information provided by the customer or on information that affects the support to the customer. A sample of these indicators is shown in Table 3-8. These indicators help to inform the facilities maintenance manager of the level of customer satisfaction and how well the maintenance organization is performing for the customer.

3.12.6.2. All of these indicators, both internal and external, are derived from metrics and applied to the specific Center. Appendix F provides an additional list and discussion of metrics that may be used to evaluate performance.

Indicator

Performance Measured

Average Duration of Work Order Processing Processing Timeliness
Actual Work Order Cost versus Estimated
Work Order Cost
Performance Efficiency
Completion Date versus Estimated Date Timeliness
Emergency Trouble Call Response Time Responsiveness
Routine Trouble Call Response Time Responsiveness
Equipment Availability Rate RCM Effectiveness
Mean Time Between Equipment Breakdown RCM Effectiveness
Percentage of Overdue PM's at End of Month RCM Management Effectiveness

Table 3-7. Internal Performance Indicators


Indicator

Performance Measured

Customer Feedback Score Customer Satisfaction
Actual Cost versus Estimate Provided to
Customer
Customer Satisfaction (indirect)
Completion Date versus Estimate Provided to Customer Customer Satisfaction (indirect)
Number of Emergency Trouble Calls/Month RCM Program Effectiveness
Cost of Unplanned versus Planned Work
Condition Assessment and Work Generation Effectiveness
Cost of Backlog of Deficiencies Level of Maintenance Funding

Table 3-8. External Performance Indicators



| TOC | Change | Preface | Chp1 | Chp2 | Chp3 | Chp4 | Chp5 | Chp6 | Chp7 | Chp8 | Chp9 | Chp10 | Chp11 | Chp12 | AppdxA | AppdxB | AppdxC | AppdxD | AppdxE | AppdxF | AppdxG | AppdxH | AppdxI | Fig12-2 | FigC-6 | FigC-7 | FigC-8 | FigD-1 | FigD-2 | FigD-3 | FigD-4 | FigD-5 | FigD-6 | FigD-7 | FigD-8 | FigD-9 | FigD-10 | FigD-11 | FigD-12 | ALL |
 
| NODIS Library | Program Management(8000s) | Search |

DISTRIBUTION:
NODIS


This Document is Obsolete and Is No Longer Used.
Check the NODIS Library to access the current version:
http://nodis3.gsfc.nasa.gov