Subject: Facility Project Requirements (FPR) (Updated w/Change 1)

Responsible Office: Office of Strategic Infrastructure


| TOC | ChangeHistory | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | Chapter7 | ApppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | AppendixK | ALL |

Appendix G. Demolition Planning Checklist

(To be used in concert with Chapter 6. Demolition/Deconstruction)

Item and Chapter 6 Reference Description Other Reference Requirements Notes Lead Time Before Demolition (Months)
Sustainment Plan- Section 6.3.3(f) Determine protection and maintenance requirements (safety, property, security, environmental) between facility deactivation and demolition. Complete as part of decommissioning.
Evaluation of alternatives and determination to demolish (HUD Determination) - Section 6.5.1.1 RPAO completes the Title V document for candidate properties and submits to FRED who interacts with HUD on behalf of the Agency. NPR 8800.15, Chapter 7 Disposition of Real Property. Evaluate disposal alternatives such as transfer to another agency or adaptive reuse (42 U.S.C. ยง 11301 et seq. screening). 12 - 24
Evaluation of alternatives, completion of the NHPA Section 106 process - Section 6.5.1.2 Determine historic eligibility, conduct alternatives analysis for historic properties, complete NHPA Section 106 review process (including mitigation), as appropriate, in accordance with the executed agreement document. NPR 8580.1, Implementing the National Environmental Policy. Also, NPR 8800.15, Chapter 7 Disposition of Real Property. If eligible, consultation with SHPO and other stakeholders may be required. 12 - 24 (prior to execution of demolition)
Authority to Dispose/Demolis h - Section 6.5.1.3 Submit a letter, signed by the Center Director or designee, requesting authority to proceed with the demolition. NPR 8800.15, Chapter 7 Disposition of Real Property. This authority is separate from the request to include the facility in the demolition program as part of the PPBES process.
Request inclusion into the Demolition Program - Section 6.6 Request funding for demolition of the facility as part of the PPBES process. Annual PPBES Guidance; NPR 8800.15, Chapter 7 Disposition of Real Property. Identify earliest demolition date and any schedule constraints. 24 - 36
Funding NASA Interagency Purchase Request (NIPR) to the USACE - Section 6.7.1 Transfer of NASA Demolition Program funding to the U.S. Army Corps of Engineers (USACE). Identify earliest demolition date and any schedule constraints. This is required only if Center's use NASA's centralized USACE demolition execution capability.
Compliance with NEPA - Section 6.7.4 Complete Record of Environmental Planning and Environmental Checklist (additional actions may be required). NPR 8580.1, Implementing the National Environmental Policy.
NPR 8800.15, Chapter 7 Disposition of Real Property.
24
Environmental Checklist - Section 6.7.4.2 Identify hazardous substances to be removed as part of demolition (asbestos, lead) and prior to demolition (chemical containers). NPR 8800.15, Chapter 7 Disposition of Real Property.
Salvage Material Inventory/ Diversion Plan - Section 6.7.6 Estimate the types and amount of materials that could have salvage value as recycled material or reuse. Evaluate how to minimize waste to landfill. NPR 8800.15, Chapter 7 Disposition of Real Property. During final design. 6 - 12
Clear the building of non-collateral equipment and debris - Section 6.7.6 Ensure that any personal property is properly disposed of separate from facility demolition. Coordinate with the Center's Property Disposal Officer. 6 - 12
Pollution Prevention and Hazardous Material Abatement Plan - Section 6.7.6 Identify potential environmental risks associated with the work such as hazardous waste disposal, run off/erosion, underground storage tank systems, wetlands, and floodplains. Determine required remediation. NPR 8800.15, Chapter 7 - Disposition of Real Property. Complete as part of building decommissioning.
Personal Property Reuse Plan - Section 6.7.8 Identify equipment, property, and artifacts for reuse by the Government or disposal by other means. NPR 8800.15, Chapter 7 Disposition of Real Property. Coordinate with the CRM, Property Disposal Officer, Program POCs, and any other special interest groups early in the process.12 - 24
Evaluate infrastructure impact - Section 6.7.9 Look at impact to utilities, roads, other facilities, physical security, etc. Demolition of a facility may remove either supply or demand of essential services, requiring modifications to associated systems. 12 - 24
Safety Baseline Survey - Section 6.7.10 Identify potential safety hazards and concerns such as:
a. Facility safety
b. Fire protection
c. Confined space entry
d. Nuclear safety
e. Radiation protection
f. Explosives
g. Pressurized systems
NPR 8800.15, Chapter 7 Disposition of Real Property. Complete as part of decommissioning.
Communication Plan (No Section Reference) Determine if a plan for communicating the content of the demolition project (and associated impacts) to the Center and the surrounding community is required. During final design. 6 - 12


| TOC | ChangeHistory | Preface | Chapter1 | Chapter2 | Chapter3 | Chapter4 | Chapter5 | Chapter6 | Chapter7 | ApppendixA | AppendixB | AppendixC | AppendixD | AppendixE | AppendixF | AppendixG | AppendixH | AppendixI | AppendixJ | AppendixK | ALL |
 
| NODIS Library | Program Management(8000s) | Search |

DISTRIBUTION:
NODIS


This document does not bind the public, except as authorized by law or as incorporated into a contract. This document is uncontrolled when printed. Check the NASA Online Directives Information System (NODIS) Library to verify that this is the correct version before use: https://nodis3.gsfc.nasa.gov.